17432 W STAGG ST 91325

Certificate Information: 17432 W STAGG ST 91325

Application / Permit
23014-20000-02589
Plan Check / Job No.
B23VN08610
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 34'-7" ADDITION TO ENLARGE (E) DETACHED ACCESSORY DWELLING UNIT. WORK TO BE DONE PER ENGINEERING.
Permit Issued
Issued on 10/16/2023
Issuing Office
Current Status
Issued on 10/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/28/2023 APPLICANT
Assigned to Plan Check Engineer 7/5/2023 JEROME MAGAT PALMA
Corrections Issued 7/5/2023 JEROME MAGAT PALMA
Building Plans Picked Up 7/6/2023 APPLICANT
Issued 10/16/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2023 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/13/2023 MARKOS PEREZ-BRAN
Low Impact Development (LID) Cleared 9/11/2023 SHAHIN KHAZEY
Construction near power lines Cleared 10/13/2023 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 10/14/2023 CARLOS AGUILERA
Hold Cleared 11/6/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 11/9/2023 Corrections Issued RAUL OLAGI
Deputy Drilled-In Anchors 11/13/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/15/2023 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/22/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/21/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/21/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval RAUL OLAGI
HVAC-Rough 2/21/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/21/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/27/2024 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/27/2024 Approved RAUL OLAGI
Insulation 3/5/2024 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 3/12/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/10/2024 Approved SALVADOR MARTINEZ
Final 5/10/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 5/10/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/10/2024 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 5/10/2024 Approved SALVADOR MARTINEZ
Final 10/24/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 10/24/2024 Corrections Issued JENNIFER RABUCHIN