7242 N LASAINE AVE 91406

Certificate Information: 7242 N LASAINE AVE 91406

Application / Permit
23014-20000-02588
Plan Check / Job No.
B23VN08606
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/17/2023
Issuing Office
Valley
Current Status
Issued on 7/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/28/2023 APPLICANT
Assigned to Plan Check Engineer 6/30/2023 ARTIN ZARUKIAN
Corrections Issued 7/1/2023 ARTIN ZARUKIAN
Building Plans Picked Up 7/3/2023 APPLICANT
Plan Check Approved 7/14/2023 GURUNATH NESARAJAH
Issued 7/17/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/3/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/14/2023 ROMAN GUTIERREZ

Contact Information

Contractor Landmark Remodeling Company; Lic. No.: 1053170-B 369 S DOHENY DR SUITE 174      BEVERLY HILLS, CA 90211
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/7/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 8/10/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 9/1/2023 Corrections Issued RAUL OLAGI
Green Building Rough 9/1/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 9/6/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/6/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 9/19/2023 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/22/2023 Approved RAUL OLAGI
HVAC-Rough 9/22/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 9/22/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 9/26/2023 Corrections Issued RAUL OLAGI
Service/Power Release 9/26/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 10/2/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/2/2023 Approved RAUL OLAGI
Green Building Rough 10/2/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/10/2023 Approved RAUL OLAGI
Insulation 10/10/2023 Approved RAUL OLAGI
Drywall Nailing 10/16/2023 Approved RAUL OLAGI
ELECTRICAL-Final 11/20/2023 Approved RAUL OLAGI
Final 11/20/2023 Corrections Issued RAUL OLAGI
Green Building Final 11/20/2023 Approved RAUL OLAGI
HVAC-Final 11/20/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 11/20/2023 Approved RAUL OLAGI