14747 W HAGAR ST 91345

Certificate Information: 14747 W HAGAR ST 91345

Application / Permit
23014-20000-02574
Plan Check / Job No.
B23VN08573
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Remove (E) 18'x14' covered patio attached to (e) 18'x20' garage and Convert (E) detached garage into an adu with 1-story addition per ordinance, all work per WFPP TOTAL ADU TO BE 577 SQFT
Permit Issued
Issued on 12/15/2023
Issuing Office
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2023 APPLICANT
Assigned to Plan Check Engineer 7/3/2023 MINA HABILI
Corrections Issued 7/5/2023 MINA HABILI
Applicant returned to address corrections 11/8/2023 JAD BASMA
Plan Check Approved 12/6/2023 JAD BASMA
Issued 12/15/2023 APPLICANT
CofO in Progress 8/15/2024 JENNIFER RABUCHIN
Permit Finaled 9/10/2024 DANIEL ORRANTE
CofO Issued 9/10/2024 DANIEL ORRANTE
Permit Finaled 9/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/7/2023 RYAN KIM
Roof/Waste drainage to street Cleared 7/7/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 7/11/2023 RYAN KIM
Sewer availability Cleared 7/24/2023 RYAN KIM
Construction near power lines Cleared 10/10/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/15/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/15/2024 Partial Approval JENNIFER RABUCHIN
Sewer 3/15/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 3/15/2024 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 3/20/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/19/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/19/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 4/19/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 4/19/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/25/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 4/25/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/25/2024 Approved JENNIFER RABUCHIN
Wood Frame 4/25/2024 Approved JENNIFER RABUCHIN
Insulation 5/23/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 5/23/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 5/28/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/28/2024 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 6/5/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/26/2024 Approved JENNIFER RABUCHIN
Shower Pan 6/26/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/7/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/7/2024 Corrections Issued JENNIFER RABUCHIN
Final 8/7/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 8/7/2024 Approved JENNIFER RABUCHIN
Green Building Final 8/7/2024 Approved JENNIFER RABUCHIN
Green Building Rough 8/7/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 8/7/2024 Approved JENNIFER RABUCHIN
MERV13>=Rough 8/7/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/7/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/15/2024 Approved JENNIFER RABUCHIN
Final 8/15/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/15/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/15/2024 Approved JENNIFER RABUCHIN