6161 N RANCHITO AVE 91401

Certificate Information: 6161 N RANCHITO AVE 91401

Application / Permit
23014-20000-02559
Plan Check / Job No.
B23VN08508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Ground floor addition of 459 SF to rear of existing 1-story single family dwelling with interior remodel. All work per engineer.
Permit Issued
Issued on 9/25/2023
Issuing Office
Current Status
Issued on 9/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/27/2023 APPLICANT
Assigned to Plan Check Engineer 7/5/2023 VICTOR CHEN
Corrections Issued 7/6/2023 VICTOR CHEN
Applicant returned to address corrections 8/22/2023 VICTOR CHEN
Plan Check Approved 9/1/2023 GEORGE ALVAREZ
Issued 9/25/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/21/2023 COLIN LOREDO

Contact Information

Contractor Simply Done Inc; Lic. No.: 936059-B       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/24/2023 Partial Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 10/27/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 11/3/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/8/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 11/8/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Partial Approval RYAN SALAZAR
Wood Frame 11/15/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval RYAN SALAZAR
Insulation 11/22/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 3/7/2024 Approved RYAN SALAZAR
PLUMBING-Rough 3/7/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/29/2024 Approved RYAN SALAZAR
Green Building Rough 3/29/2024 Approved RYAN SALAZAR
HVAC-Rough 3/29/2024 Approved RYAN SALAZAR
Insulation 3/29/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/29/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 4/11/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/29/2024 Approved RYAN SALAZAR
Shower Pan 4/29/2024 Approved RYAN SALAZAR
Green Building Final 7/12/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 7/12/2024 Not Ready for Inspection RYAN SALAZAR
Final 7/19/2024 Partial Approval RYAN SALAZAR
Green Building Final 7/19/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 7/19/2024 Approved RYAN SALAZAR
Smoke Detectors 7/19/2024 Approved RYAN SALAZAR
Final 8/30/2024 Partial Approval RYAN SALAZAR