6253 N WILLOW CREST AVE 91606

Certificate Information: 6253 N WILLOW CREST AVE 91606

Application / Permit
23014-20000-02545
Plan Check / Job No.
B23VN08480
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (N) 14'-7" x 15'-2" AND CONVERT (E) 20'-0" x 18'-0" DETACHED GARAGE INTO A (N) IRREGULAR SHAPED DETACHED 34'-7" x 18'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) and (d), work per WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 05/18/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/20/2023
Issuing Office
Current Status
CofO Issued on 2/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2023 APPLICANT
Assigned to Plan Check Engineer 6/30/2023 RAMA DABADGE
Corrections Issued 7/3/2023 RAMA DABADGE
Building Plans Picked Up 7/5/2023 APPLICANT
Applicant returned to address corrections 7/17/2023 ALFRED RAMIREZ
Plan Check Approved 7/20/2023 GIOVANNY CHAVEZ
Issued 7/20/2023 APPLICANT
CofO in Progress 1/10/2024 THOMAS WOODS
CofO Issued 2/23/2024 DAVID JAMES
Permit Finaled 2/23/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 7/6/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/6/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/6/2023 TAL SHEMEN
Sewer availability Cleared 7/6/2023 TAL SHEMEN
Public Works-Highway Ded. Cleared 7/6/2023 TAL SHEMEN
Public Works-Open Permits Cleared 7/6/2023 TAL SHEMEN
Public Works-Sewers Cleared 7/6/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/9/2023 Approved THOMAS WOODS
Deputy Drilled-In Anchors 8/14/2023 No Result Entered MARSHALL RUMPF
Excavation/Setback/Form/Re-Bar 8/16/2023 Approved THOMAS WOODS
Sewer 8/16/2023 Approved THOMAS WOODS
BUILDING-Rough-Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
Green Building Rough 8/29/2023 Not Ready for Inspection THOMAS WOODS
Light Gage Steel Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
Reinforced Concrete Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
Reinforced Masonry Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
Structural Steel Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
Wood Frame 8/29/2023 Not Ready for Inspection THOMAS WOODS
ELECTRICAL-Rough 9/19/2023 Approved THOMAS WOODS
Green Building Rough 9/19/2023 Approved THOMAS WOODS
PLUMBING-Rough 9/19/2023 Approved THOMAS WOODS
Wood Frame 9/19/2023 Approved THOMAS WOODS
Insulation 9/25/2023 Approved THOMAS WOODS
Drywall Nailing 10/12/2023 Approved THOMAS WOODS
Shower Pan 10/12/2023 Approved THOMAS WOODS
Interior/Exterior Lathing 10/17/2023 Approved THOMAS WOODS
ELECTRICAL-Final 11/29/2023 Corrections Issued THOMAS WOODS
Final 11/29/2023 Not Ready for Inspection THOMAS WOODS
Green Building Final 11/29/2023 Corrections Issued THOMAS WOODS
HVAC-Final 11/29/2023 Approved THOMAS WOODS
PLUMBING-Final 11/29/2023 Approved THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready THOMAS WOODS
Smoke Detectors 11/29/2023 Corrections Issued THOMAS WOODS
BUILDING-Rough-Frame 12/7/2023 Approved THOMAS WOODS
ELECTRICAL-Final 12/7/2023 Corrections Issued THOMAS WOODS
Final 12/7/2023 Not Ready for Inspection THOMAS WOODS
Footing/Foundation/Slab 12/7/2023 Approved THOMAS WOODS
Green Building Final 12/7/2023 Approved THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved THOMAS WOODS
Smoke Detectors 12/7/2023 Approved THOMAS WOODS
ELECTRICAL-Final 1/10/2024 Approved THOMAS WOODS
Final 1/10/2024 OK to Issue CofO THOMAS WOODS