3662 N GOODLAND AVE 91604
Certificate Information: 3662 N GOODLAND AVE 91604
- Application / Permit
- 23014-20000-02537
- Plan Check / Job No.
- B23VN08429
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 3' x 8'-8" ADDITION AT REAR (27 SF) OF (E) ONE-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND (N) 2ND FLOOR ADDITION (1,210 SF), AND REMODEL; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 10/5/2023
- Issuing Office
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | SEAN SHAHMIRI |
| Corrections Issued | 7/5/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 7/6/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/7/2023 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/20/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 10/5/2023 | SEAN SHAHMIRI |
| Issued | 10/5/2023 | APPLICANT |
| CofO in Progress | 7/31/2024 | CHRISTOPHE COCHRAN |
| CofO Issued | 11/13/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/13/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/13/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/22/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/28/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/4/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/6/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 9/11/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 10/5/2023 | SEAN SHAHMIRI |
Contact Information
| Contractor | Nittay Inc; Lic. No.: 1033506-B | 17941 VENTURA BLVD #204 ENCINO, CA 91316 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/13/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/14/2023 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 1/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 1/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 1/18/2024 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 1/22/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/29/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 1/29/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/1/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/2/2024 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/6/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/6/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/12/2024 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 2/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 2/16/2024 | Conditional Approval | CHRISTOPHE COCHRAN |
| Insulation | 2/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 2/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 2/23/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/10/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 6/10/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 6/10/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 6/10/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/20/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 6/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 7/31/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 7/31/2024 | Approved | CHRISTOPHE COCHRAN |