8714 S CIMARRON ST 90047
Certificate Information: 8714 S CIMARRON ST 90047
- Application / Permit
- 23014-20000-02517
- Plan Check / Job No.
- B23VN08364
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 33'-6" X 25'-5" IRREGULAR SHAPED ADDITION TO (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 9/27/2023
- Issuing Office
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/29/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/7/2023 | APPLICANT |
| Issued | 9/27/2023 | APPLICANT |
| CofO in Progress | 5/22/2025 | MICHAEL LEWIS |
| Permit Finaled | 5/23/2025 | DEROLD HAUFF |
| CofO Issued | 5/23/2025 | DEROLD HAUFF |
| Permit Finaled | 5/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 7/16/2023 | AHMED AMARRAGY |
| Low Impact Development (LID) | Cleared | 9/18/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/23/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Cali Builders & Construction Inc; Lic. No.: 1051566-B | 15130 VENTURA BLVD STE 250 LOS ANGELES, CA 91403 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2024 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 8/27/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| METHANE-Rough | 9/4/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 9/4/2024 | Partial Approval | AMIR NAZARIAN |
| Insulation | 9/6/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2024 | Partial Approval | MICHAEL LEWIS |
| Sewer | 9/6/2024 | Partial Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/24/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/27/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/1/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/4/2024 | Corrections Issued | LUIS CASTRO |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | LUIS CASTRO |
| Insulation | 10/4/2024 | Corrections Issued | LUIS CASTRO |
| Insulation | 10/8/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/9/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Rough | 10/9/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/9/2024 | Partial Approval | AMIR NAZARIAN |
| Shower Pan | 10/9/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/17/2024 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 10/17/2024 | Conditional Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/17/2024 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 10/22/2024 | Conditional Approval | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/22/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 10/22/2024 | Approved | AMIR NAZARIAN |
| Wood Frame | 10/22/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/24/2024 | Conditional Approval | ALEX COLIN |
| Drywall Nailing | 10/30/2024 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 2/26/2025 | Approved | MICHAEL LEWIS |
| Final | 2/26/2025 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 2/26/2025 | Approved | MICHAEL LEWIS |
| Green Building Final | 2/26/2025 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 2/26/2025 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 2/26/2025 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 2/26/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 4/22/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Smoke Detectors | 4/22/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 4/29/2025 | Corrections Issued | WAYNE REGESTER |
| Smoke Detectors | 4/29/2025 | Approved | WAYNE REGESTER |
| Final | 5/12/2025 | Partial Approval | WAYNE REGESTER |
| Final | 5/19/2025 | Partial Approval | WAYNE REGESTER |
| Final | 5/22/2025 | OK to Issue CofO | WAYNE REGESTER |