13247 W RAVEN ST 91342
Certificate Information: 13247 W RAVEN ST 91342
- Application / Permit
- 23014-20000-02514
- Plan Check / Job No.
- B23VN08351
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 23'-3" X 21'-11" ADDITION INCLUDING CONVERSION OF (E) PATIO COVER TO LIVING AREA TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/19/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/21/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/14/2023 | APPLICANT |
| Applicant returned to address corrections | 9/16/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 12/27/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/24/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | KEVIN BERBERYAN |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/22/2023 | NIKKI ZULUETA |
| Grading Pre-Inspection | Cleared | 11/13/2023 | SERGIO VALENZUELA |
| Low Impact Development (LID) | Cleared | 11/13/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/17/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 12/27/2024 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/28/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 3/21/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 5/22/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 6/10/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/10/2025 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 6/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 6/13/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 6/13/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 6/17/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/17/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/1/2025 | Approved | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 12/19/2025 | Conditional Approval | RAUL OLAGI |
| Service/Power Release | 12/29/2025 | Approved | KEVIN BERBERYAN |
| Final | 2/25/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 2/25/2026 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 2/25/2026 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 3/5/2026 | Approved | KEVIN BERBERYAN |