13247 W RAVEN ST 91342

Certificate Information: 13247 W RAVEN ST 91342

Application / Permit
23014-20000-02514
Plan Check / Job No.
B23VN08351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) 23'-3" X 21'-11" ADDITION INCLUDING CONVERSION OF (E) PATIO COVER TO LIVING AREA TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 1/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/19/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/21/2023 OMID HEDAYAT
Building Plans Picked Up 8/14/2023 APPLICANT
Applicant returned to address corrections 9/16/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/27/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/24/2025 SEWADA ZADOORAN MILAGARDI
Issued 1/24/2025 APPLICANT
CofO in Progress 3/5/2026 KEVIN BERBERYAN
Permit Finaled 3/26/2026 RUBEN SALAS
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/21/2023 NIKKI ZULUETA
Sewer availability Cleared 8/22/2023 NIKKI ZULUETA
Grading Pre-Inspection Cleared 11/13/2023 SERGIO VALENZUELA
Low Impact Development (LID) Cleared 11/13/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 12/17/2024 CARLOS AGUILERA
GPI Written Notices Cleared 12/27/2024 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/28/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 2/28/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/21/2025 Partial Approval KEVIN BERBERYAN
Sewer 3/21/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 5/22/2025 Approved KEVIN BERBERYAN
Gas Test 5/22/2025 Approved KEVIN BERBERYAN
Gas Test 6/10/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/10/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 6/10/2025 Corrections Issued KEVIN BERBERYAN
Insulation 6/13/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/13/2025 Approved LOUIS ESCOTO
Drywall Nailing 6/17/2025 Approved KEVIN BERBERYAN
Green Building Rough 6/17/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/1/2025 Approved KEVIN BERBERYAN
Deputy Reinf. Concrete 12/19/2025 Conditional Approval RAUL OLAGI
Service/Power Release 12/29/2025 Approved KEVIN BERBERYAN
Final 2/25/2026 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 2/25/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 2/25/2026 Approved KEVIN BERBERYAN
Service/Power Release 3/5/2026 Approved KEVIN BERBERYAN