13245 W RAVEN ST 91342

Certificate Information: 13245 W RAVEN ST 91342

Application / Permit
23014-20000-02513
Plan Check / Job No.
B23VN08351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (N) 30'-6" X 25'-4" TO (E) 20' X 18' GARAGE AND CONVERT ENTIRE STRUCTURE TO A ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 1/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/19/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/21/2023 OMID HEDAYAT
Building Plans Picked Up 8/14/2023 APPLICANT
Applicant returned to address corrections 9/16/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/27/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/24/2025 SEWADA ZADOORAN MILAGARDI
Issued 1/24/2025 APPLICANT
CofO in Progress 3/5/2026 KEVIN BERBERYAN
Permit Finaled 3/26/2026 RUBEN SALAS
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/19/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 8/21/2023 NIKKI ZULUETA
Sewer availability Cleared 8/22/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 11/13/2023 MELINEH AGHAKHABIAN
Grading Pre-Inspection Cleared 12/13/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 12/17/2024 CARLOS AGUILERA
GPI Written Notices Cleared 12/27/2024 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2025 Partial Inspection KEVIN BERBERYAN
Sewer 2/21/2025 Approved KEVIN BERBERYAN
Underground Mechanical 2/21/2025 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 2/25/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 2/26/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 2/26/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 5/9/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/22/2025 Conditional Approval KEVIN BERBERYAN
Underground Mechanical 5/22/2025 Approved KEVIN BERBERYAN
Gas Test 6/10/2025 Approved KEVIN BERBERYAN
Green Building Rough 6/10/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/10/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 6/10/2025 Approved KEVIN BERBERYAN
Insulation 6/13/2025 Approved LOUIS ESCOTO
Drywall Nailing 6/17/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/25/2025 Approved KEVIN BERBERYAN
Shower Pan 6/25/2025 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 7/15/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 11/21/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 11/21/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 11/21/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 11/21/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 11/21/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 11/21/2025 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 11/21/2025 Approved KEVIN BERBERYAN
Final 12/9/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/9/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved KEVIN BERBERYAN
Final 2/25/2026 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 2/25/2026 Approved KEVIN BERBERYAN