261 W 43RD PL 90037

Certificate Information: 261 W 43RD PL 90037

Application / Permit
23014-20000-02507
Plan Check / Job No.
B23VN08317
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan (n) Addition to Single Family dwelling per WFPP.
Permit Issued
Issued on 7/29/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 KHUONG TRUONG
Corrections Issued 6/23/2023 KHUONG TRUONG
Applicant returned to address corrections 7/6/2023 DANIEL SMILEY
Plan Check Approved 7/26/2023 ZAW HAN
Issued 7/29/2023 APPLICANT
CofO in Progress 9/3/2024 ALEJANDRO DE ARTOLA
Permit Finaled 9/17/2024 RUBEN SALAS
CofO Issued 9/17/2024 RUBEN SALAS
Permit Finaled 9/17/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/27/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 6/27/2023 WALLIE JONG
Sewer availability Cleared 6/27/2023 WALLIE JONG
Low Impact Development (LID) Cleared 7/24/2023 SAMUEL LINN

Contact Information

Contractor Roof Replacement Inc; Lic. No.: 1063655-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2023 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/7/2023 Approved ALEJANDRO DE ARTOLA
Wood Frame 8/10/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 12/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 1/2/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/2/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/4/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/4/2024 Approved SABAS ALONSO
Green Building Rough 1/4/2024 Approved SABAS ALONSO
MERV13>=Rough 1/4/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/9/2024 Approved ENRIQUE MIRELES
MERV13>=Rough 1/9/2024 Approved ENRIQUE MIRELES
Insulation 1/12/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 1/12/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/19/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/19/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 6/6/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 6/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/17/2024 No Access for Inspection DAVID FEILER
Final 6/17/2024 No Access for Inspection DAVID FEILER
Green Building Final 6/17/2024 No Access for Inspection DAVID FEILER
HVAC-Final 6/17/2024 No Access for Inspection DAVID FEILER
PLUMBING-Final 6/17/2024 No Access for Inspection DAVID FEILER
Smoke Detectors 6/17/2024 No Access for Inspection DAVID FEILER
ELECTRICAL-Final 6/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 6/20/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/25/2024 Approved ALEJANDRO DE ARTOLA
Final 6/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/25/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/25/2024 Approved ALEJANDRO DE ARTOLA
Final 8/9/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 8/9/2024 Partial Inspection MICHAEL LEWIS
Final 8/15/2024 Conditional Approval BRENDAN MORELLI
Green Building Final 8/15/2024 Approved BRENDAN MORELLI
Final 8/30/2024 OK to Issue CofO ALEJANDRO DE ARTOLA