815 1/2 S ORANGE DR 90036

Certificate Information: 815 1/2 S ORANGE DR 90036

Application / Permit
23014-20000-02491
Plan Check / Job No.
B23VN08284
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 18'4"X20' DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 15'8"X16' ADDN. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 12/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/28/2023 JESSE ARELLANO
Corrections Issued 6/29/2023 JESSE ARELLANO
Building Plans Picked Up 6/30/2023 APPLICANT
Plan Check Approved 11/9/2023 HAYATO TSUCHIYA
Issued 12/27/2023 APPLICANT
CofO in Progress 12/3/2024 RONNIE MINDANAO
CofO in Progress 1/21/2025 RONNIE MINDANAO
Permit Finaled 1/26/2025 DEROLD HAUFF
CofO Issued 1/26/2025 DEROLD HAUFF
Permit Finaled 1/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/30/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/30/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 6/30/2023 WALLIE JONG
Sewer availability Cleared 6/30/2023 WALLIE JONG
ZA Case Cleared 8/3/2023 STEVEN WECHSLER
Construction near power lines Cleared 11/6/2023 RIDWAN HARDY

Contact Information

Contractor Caland Inc; Lic. No.: 940773-B 1212 SOUTH STANLEY AVENUE      LOS ANGELES, CA 90019

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/15/2024 Approved AMIR NAZARIAN
Underground Mechanical 2/15/2024 Not Ready for Inspection AMIR NAZARIAN
Footing/Foundation/Slab 3/7/2024 Corrections Issued RONNIE MINDANAO
METHANE-Barrier 3/7/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 3/7/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 4/17/2024 Conditional Approval AMIR NAZARIAN
Deputy Reinf. Concrete 4/18/2024 Conditional Approval AMIR NAZARIAN
BUILDING-Rough-Frame 7/10/2024 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 7/10/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 7/10/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Approved RONNIE MINDANAO
Deputy Wood Construction 7/15/2024 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 7/19/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 7/29/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Corrections Issued RONNIE MINDANAO
Green Building Rough 7/29/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 7/29/2024 Corrections Issued RONNIE MINDANAO
METHANE-Rough 7/29/2024 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 8/7/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 8/7/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Approved RONNIE MINDANAO
Green Building Rough 8/7/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 8/7/2024 Corrections Issued RONNIE MINDANAO
METHANE-Rough 8/7/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 8/9/2024 Conditional Approval RONNIE MINDANAO
ELECTRICAL-Rough 8/9/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Approved RONNIE MINDANAO
Green Building Rough 8/9/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 8/9/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 8/9/2024 Approved RONNIE MINDANAO
Insulation 8/16/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 8/16/2024 Approved RONNIE MINDANAO
Shower Pan 8/22/2024 Approved RONNIE MINDANAO
Drywall Nailing 8/27/2024 Approved RONNIE MINDANAO
Green Building Rough 8/27/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 8/27/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 11/21/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 11/21/2024 Approved RONNIE MINDANAO
Final 11/21/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 11/21/2024 Approved RONNIE MINDANAO
Green Building Final 11/21/2024 Approved RONNIE MINDANAO
HVAC-Final 11/21/2024 Approved RONNIE MINDANAO
PLUMBING-Final 11/21/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Not Required RONNIE MINDANAO
Service/Power Release 11/21/2024 Approved RONNIE MINDANAO
Smoke Detectors 11/21/2024 Approved RONNIE MINDANAO
ELECTRICAL-Final 12/3/2024 Approved RONNIE MINDANAO
Final 12/3/2024 OK to Issue CofO RONNIE MINDANAO
HVAC-Final 12/3/2024 Approved RONNIE MINDANAO
PLUMBING-Final 12/3/2024 Approved RONNIE MINDANAO
Final 1/21/2025 OK to Issue CofO RONNIE MINDANAO
Special/Order Compliance 1/24/2025 Approved RONNIE MINDANAO