14233 W TIARA ST 91401
Certificate Information: 14233 W TIARA ST 91401
- Application / Permit
- 23014-20000-02484
- Plan Check / Job No.
- B23VN08244
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADD (N) 11' x 30' ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) & (e)] TO (E) 3-UNIT APARTMENT BLDG; NFPA 13R FIRE SPRINKLERS THROUGHOUT; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Valley
- Current Status
- Issued on 1/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2023 | JESSE ARELLANO |
| Corrections Issued | 6/29/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 6/30/2023 | APPLICANT |
| Plan Check Approved | 1/8/2024 | SEAN SHAHMIRI |
| Issued | 1/8/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/7/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 8/7/2023 | BRENNEN OBETO |
| Address approval | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/18/2023 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 10/21/2023 | RIDWAN HARDY |
| DAS Clearance | Cleared | 12/18/2023 | SEAN SHAHMIRI |
| Green Code | Cleared | 1/8/2024 | SEAN SHAHMIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nourmohammadi,, Khosrow; Lic. No.: C71141 | 2515 BAMBOO NEWPORT BEACH, CA 92660 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | STEVEN LEVITT |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Approved | STEVEN LEVITT |
| Special/Order Compliance | 3/11/2024 | Partial Inspection | MELVIN GIRTON |
| Green Building Rough | 5/2/2024 | Approved | STEVEN LEVITT |
| Wood Frame | 5/2/2024 | Approved | STEVEN LEVITT |
| Insulation | 5/7/2024 | Approved | STEVEN LEVITT |
| Interior/Exterior Lathing | 5/16/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 5/17/2024 | Approved | STEVEN LEVITT |
| Final | 9/18/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Footing/Foundation/Slab | 9/18/2024 | Approved | STEVEN LEVITT |
| Green Building Final | 9/18/2024 | Approved | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | STEVEN LEVITT |
| Smoke Detectors | 9/18/2024 | Approved | STEVEN LEVITT |
| Final | 10/18/2024 | Conditional Approval | STEVEN LEVITT |