2009 N SERRANO AVE 90027
Certificate Information: 2009 N SERRANO AVE 90027
- Application / Permit
- 23014-20000-02454
- Plan Check / Job No.
- B23VN08126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (14'-2"x10'-4"), 142 SQFT 2ND STORY ADDITION ABOVE EXISTING SINGLE FAMILY DWELLING, ALL WORK DONE OVER EXISTING FOOTPRINT.
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | PETER MOSESIAN |
| Corrections Issued | 6/29/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/3/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/5/2023 | APPLICANT |
| Plan Check Approved | 8/17/2023 | PETER MOSESIAN |
| Issued | 8/22/2023 | APPLICANT |
| CofO in Progress | 5/21/2024 | BRIAN SULLIVAN |
| CofO Issued | 5/21/2024 | RONALD MYRICK |
| Permit Finaled | 5/21/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/28/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 8/17/2023 | PETER MOSESIAN |
Contact Information
| Contractor | Ts Construction & Design Inc; Lic. No.: 1064916-B | 18375 VENTURA BLVD #375 TARZANA, CA 91356 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/5/2023 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 9/29/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/4/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 10/4/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/16/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/16/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/16/2023 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 10/16/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/20/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 10/20/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 10/25/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 11/21/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/21/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/21/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 11/21/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 5/10/2024 | Approved | BRIAN SULLIVAN |
| Final | 5/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/10/2024 | Approved | BRIAN SULLIVAN |
| Green Building Final | 5/10/2024 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 5/10/2024 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 5/10/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 5/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| Final | 5/20/2024 | OK to Issue CofO | BRIAN SULLIVAN |
| Smoke Detectors | 5/20/2024 | Approved | BRIAN SULLIVAN |