6728 N JUMILLA AVE 91306

Certificate Information: 6728 N JUMILLA AVE 91306

Application / Permit
23014-20000-02442
Plan Check / Job No.
B23VN08102
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 17' X 17' ADDITION TO (E) DETACHED ACCESORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 10/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 JESSE ARELLANO
Corrections Issued 6/24/2023 JESSE ARELLANO
Building Plans Picked Up 7/11/2023 APPLICANT
Applicant returned to address corrections 9/21/2023 LUISANGEL VALENZUELA
Plan Check Approved 10/6/2023 MADISON ODELL
Issued 10/13/2023 APPLICANT
CofO in Progress 3/4/2024 ARUTYUN MADATYAN
Permit Finaled 3/22/2024 JOHN JANSON
CofO Issued 3/22/2024 JOHN JANSON
Permit Finaled 3/22/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/22/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/29/2023 CARLOS AGUILERA
Sewer availability Cleared 9/29/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 11/17/2023 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 11/29/2023 No Access for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/1/2023 Approved ALEXANDER HANDY
ELECTRICAL-Rough 12/1/2023 Approved ALEXANDER HANDY
Green Building Rough 12/1/2023 Approved ALEXANDER HANDY
HVAC-Rough 12/1/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 12/1/2023 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 12/1/2023 Approved ALEXANDER HANDY
Insulation 12/8/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 12/8/2023 Approved ALEXANDER HANDY
Shower Pan 12/8/2023 Approved ALEXANDER HANDY
Drywall Nailing 12/13/2023 Approved ALEXANDER HANDY
Final 2/1/2024 Corrections Issued MORRIS JACKSON
Green Building Final 2/1/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 2/1/2024 Not Ready for Inspection MORRIS JACKSON
Final 2/16/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 2/16/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 2/23/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 2/23/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/1/2024 Approved ARUTYUN MADATYAN
Final 3/1/2024 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 3/1/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/1/2024 Approved ARUTYUN MADATYAN