5331 N FULTON AVE 91401

Certificate Information: 5331 N FULTON AVE 91401

Application / Permit
23014-20000-02438
Plan Check / Job No.
B23VN08091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 8/2/2023
Issuing Office
Valley
Current Status
Issued on 8/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 SERGIO MUNIZ
Corrections Issued 6/24/2023 SERGIO MUNIZ
Building Plans Picked Up 7/6/2023 APPLICANT
Applicant returned to address corrections 7/19/2023 MOHAMMAD ESMAILI
Plan Check Approved 8/2/2023 ROSENDO MEDINA
Issued 8/2/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/1/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 8/1/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/1/2023 NIKKI ZULUETA

Contact Information

Contractor Be Green Builders Inc; Lic. No.: 1036245-B 4220 LONGRIDGE AVE #205      STUDIO CITY, CA 91604
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/9/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/9/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/14/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/17/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 9/11/2023 Corrections Issued MISAEL ESPARZA
Insulation 9/14/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 11/14/2023 Approved MISAEL ESPARZA
Green Building Rough 11/14/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/14/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/14/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 11/16/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/16/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/29/2023 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/29/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 11/29/2023 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 11/29/2023 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/7/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/7/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/12/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/12/2024 Not Ready for Inspection MISAEL ESPARZA
Insulation 2/28/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/28/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 3/12/2024 Approved MISAEL ESPARZA
Shower Pan 3/12/2024 Approved MISAEL ESPARZA
Drywall Nailing 3/19/2024 Approved MISAEL ESPARZA
Gas Test 7/24/2024 Corrections Issued JACK KARGODORIAN
Gas Test 7/26/2024 Approved JOSE AVILA
ELECTRICAL-Final 7/31/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 7/31/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/31/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/2/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 8/2/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/2/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/6/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/6/2024 Approved MISAEL ESPARZA
Final 8/6/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 8/6/2024 Approved MISAEL ESPARZA
Green Building Rough 8/6/2024 Approved MISAEL ESPARZA
HVAC-Final 8/6/2024 Approved MISAEL ESPARZA
PLUMBING-Final 8/6/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/6/2024 Approved MISAEL ESPARZA