1422-1424 S BEVERWIL DR 90035
Certificate Information: 1422-1424 S BEVERWIL DR 90035
- Application / Permit
- 23014-20000-02417
- Plan Check / Job No.
- B23VN08028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW IRR. SHAPED 31'-10" x 45' 2ND FLOOR ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) and (e)] TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- Issued on 9/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | SEAN SHAHMIRI |
| Corrections Issued | 6/26/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 6/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/30/2023 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 9/7/2023 | SEAN SHAHMIRI |
| Issued | 9/7/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 8/3/2023 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 8/4/2023 | ROBERT HUGHES |
| Low Impact Development (LID) | Cleared | 8/28/2023 | MEGAN PINKUS |
| Roof/Waste drainage to street | Cleared | 8/30/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 8/5/2024 | Partial Inspection | REGINA MENDEZ |
| Footing/Foundation/Slab | 12/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 12/20/2024 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 12/30/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 12/30/2024 | Partial Approval | STEPHANIE SWANSON |
| Structural Steel Frame | 12/30/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Deputy Steel/Welding | 1/3/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 1/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Structural Steel Frame | 1/3/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | No Access for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 3/14/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/4/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/4/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 4/28/2025 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 5/22/2025 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 5/22/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 10/16/2025 | No Access for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/20/2025 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 10/20/2025 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 10/20/2025 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Rough | 10/20/2025 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 10/22/2025 | No Access for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/22/2025 | No Access for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 10/24/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/24/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 11/10/2025 | Not Ready for Inspection | ASHLEY THOMPSON |