18033 W ERWIN ST 91316
Certificate Information: 18033 W ERWIN ST 91316
- Application / Permit
- 23014-20000-02415
- Plan Check / Job No.
- B23VN08024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 19'-3" x 8'-0" ADDITION TO (E) SFD. ADD (N) 13'-8"X14'-3" ATTACHED PATIO COVER PER CITY STD PLAN. WORK PER WFPP.
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Valley
- Current Status
- Issued on 1/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | JESSE ARELLANO |
| Corrections Issued | 6/23/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 6/30/2023 | APPLICANT |
| Applicant returned to address corrections | 9/29/2023 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/6/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 10/20/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/26/2024 | ISIS ARGUETA |
| Issued | 1/26/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/29/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2024 | No Access for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 10/25/2024 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 3/21/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 4/11/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/25/2025 | Partial Approval | DAVID SCANTLIN |
| Insulation | 4/25/2025 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | DAVID SCANTLIN |
| Drywall Nailing | 5/2/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 9/19/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 9/19/2025 | Not Ready for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Not Required | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/18/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 3/18/2026 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 3/18/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Final | 3/18/2026 | Approved | MORRIS JACKSON |
| Green Building Rough | 3/18/2026 | Approved | MORRIS JACKSON |