10125-10127 W VALLEY SPRING LANE 91602

Certificate Information: 10125-10127 W VALLEY SPRING LANE 91602

Application / Permit
23014-20000-02393
Plan Check / Job No.
B23VN07927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 1ST FLOOR AND 2ND FLOOR ADDITION TO (E) 2-STORY SFD WITH (N) ATT. GARAGE CONVERT (E) GARAGE WITH NEW ADDITION TO ADU PER LAMC 12.22 A33 (c) & (e)
Permit Issued
Issued on 8/18/2023
Issuing Office
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 MAHNAZ NOURHASHEMI
Corrections Issued 6/30/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 7/7/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/8/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 8/16/2023 MAHNAZ NOURHASHEMI
Issued 8/18/2023 APPLICANT
CofO in Progress 4/9/2026 JAVIER RAMOS JR
CofO Issued 6/23/2026 RUBEN SALAS
Permit Finaled 6/23/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/10/2023 TAL SHEMEN
Permit Cleared 7/10/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/11/2023 TAL SHEMEN
Sewer availability Cleared 7/11/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 7/26/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 7/26/2023 TAL SHEMEN
ZI Cleared 7/26/2023 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/15/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 5/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 5/21/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/21/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 7/2/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/8/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/15/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/19/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/24/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 8/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 8/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 9/6/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 12/19/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/19/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/29/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/29/2025 Partial Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/29/2025 Partial Inspection CHRISTOPHER ROJAS
Pre-Inspection 1/31/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/4/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/4/2025 Approved JAVIER RAMOS JR
Green Building Rough 4/4/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/4/2025 Partial Approval JAVIER RAMOS JR
Insulation 4/14/2025 Approved JAVIER RAMOS JR
Service/Power Release 4/14/2025 Approved JAVIER RAMOS JR
Shower Pan 4/14/2025 Approved JAVIER RAMOS JR
Drywall Nailing 4/25/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 4/25/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 1/6/2026 Corrections Issued CRAIG DAVIS
HVAC-Final 1/6/2026 Corrections Issued CRAIG DAVIS
PLUMBING-Final 1/6/2026 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 3/16/2026 Corrections Issued JAVIER RAMOS JR
Final 3/16/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/16/2026 Approved JAVIER RAMOS JR
HVAC-Final 3/16/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 3/16/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/16/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/23/2026 Approved JAVIER RAMOS JR
Final 4/8/2026 OK to Issue CofO JAVIER RAMOS JR