10348 N LANGDON AVE 91345
Certificate Information: 10348 N LANGDON AVE 91345
- Application / Permit
- 23014-20000-02385
- Plan Check / Job No.
- B23VN07899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 19'-0' x 14'-6" ADDITION TO THE SINGLE FAMILY DWELLING. NEW 6'-0" x 14'-6" OPEN PATIO ADDITION TO THE SINGLE FAMILY DWELLING. WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2023 | SERGIO MUNIZ |
| Corrections Issued | 6/22/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/6/2023 | APPLICANT |
| Applicant returned to address corrections | 8/29/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/13/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/14/2023 | GIOVANNY CHAVEZ |
| Issued | 9/14/2023 | APPLICANT |
| CofO in Progress | 3/11/2024 | JENNIFER RABUCHIN |
| CofO in Progress | 3/19/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Watercourse | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Final | 9/20/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/20/2023 | Approved | JENNIFER RABUCHIN |
| Final | 9/27/2023 | OK to Issue CofO | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/11/2024 | Approved | JENNIFER RABUCHIN |
| Final | 3/11/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 3/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/11/2024 | Approved | JENNIFER RABUCHIN |