6635 N RIVERTON AVE 91606
Certificate Information: 6635 N RIVERTON AVE 91606
- Application / Permit
- 23014-20000-02365
- Plan Check / Job No.
- B23VN07838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE CONVERSION TO ACCESSORY DWELLING UNIT AND IRREGULAR SHAPED 29'-5" x 31'-8" ADDITION. WORK DONE PER WFPP AND ENGINEERING.
- Permit Issued
- Issued on 8/2/2023
- Issuing Office
- Current Status
- CofO Issued on 3/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | SERGIO MUNIZ |
| Corrections Issued | 6/16/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/23/2023 | APPLICANT |
| Plan Check Approved | 7/31/2023 | GIOVANNY CHAVEZ |
| Issued | 8/2/2023 | APPLICANT |
| CofO in Progress | 2/5/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
| CofO Issued | 3/15/2024 | RUBEN SALAS |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/28/2023 | ROGELIO CORTES |
| Address approval | Cleared | 6/29/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | ROMAN GUTIERREZ |
| Construction within easement | Cleared | 7/29/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 9/21/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 9/26/2023 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 10/2/2023 | Approved | JOHN HAYES |
| Sewer | 10/6/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 10/17/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/27/2023 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 10/27/2023 | Approved | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 10/27/2023 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 11/2/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 11/2/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 11/2/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/7/2023 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 11/7/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Approved | JOHN HAYES |
| Insulation | 11/14/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 11/20/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/1/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 1/30/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/2/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/2/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/2/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/2/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | JENNIFER RABUCHIN |