6634 N SALOMA AVE 91405
Certificate Information: 6634 N SALOMA AVE 91405
- Application / Permit
- 23014-20000-02353
- Plan Check / Job No.
- B23VN07785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET GARAGE TO ADU WITH ADDITION PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | SERGIO MUNIZ |
| Corrections Issued | 6/17/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/23/2023 | APPLICANT |
| Applicant returned to address corrections | 6/30/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/10/2023 | PINANK PATEL |
| Issued | 10/10/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | RYAN SALAZAR |
| Permit Finaled | 3/29/2024 | RONALD MYRICK |
| CofO Issued | 3/29/2024 | RONALD MYRICK |
| Permit Finaled | 3/29/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 6/27/2023 | STEVEN WECHSLER |
| Sewer availability | Cleared | 6/27/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/29/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/29/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/5/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Az Vision Remodeling; Lic. No.: 1015050-B | 11909 TIARA STREET VALLEY VILLAGE, CA 91607 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2023 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/26/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 10/26/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/29/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/8/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/8/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/8/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 12/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/8/2023 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/8/2023 | Approved | RYAN SALAZAR |
| Insulation | 12/13/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/13/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 12/13/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/18/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/29/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/29/2024 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/29/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 1/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 1/29/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/31/2024 | Approved | RYAN SALAZAR |
| Final | 1/31/2024 | OK to Issue CofO | RYAN SALAZAR |
| Gas Test | 1/31/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 1/31/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/31/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 1/31/2024 | Approved | RYAN SALAZAR |