6634 N SALOMA AVE 91405

Certificate Information: 6634 N SALOMA AVE 91405

Application / Permit
23014-20000-02353
Plan Check / Job No.
B23VN07785
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE TO ADU WITH ADDITION PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/10/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 SERGIO MUNIZ
Corrections Issued 6/17/2023 SERGIO MUNIZ
Building Plans Picked Up 6/23/2023 APPLICANT
Applicant returned to address corrections 6/30/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 10/10/2023 PINANK PATEL
Issued 10/10/2023 APPLICANT
CofO in Progress 2/1/2024 RYAN SALAZAR
Permit Finaled 3/29/2024 RONALD MYRICK
CofO Issued 3/29/2024 RONALD MYRICK
Permit Finaled 3/29/2024 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 6/26/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/27/2023 CARLOS AGUILERA
Miscellaneous Cleared 6/27/2023 STEVEN WECHSLER
Sewer availability Cleared 6/27/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/29/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/29/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 10/5/2023 RIDWAN HARDY

Contact Information

Contractor Az Vision Remodeling; Lic. No.: 1015050-B 11909 TIARA STREET      VALLEY VILLAGE, CA 91607
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2023 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 10/26/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 10/26/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 10/27/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Approved RYAN SALAZAR
PLUMBING-Rough 11/29/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/8/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 12/8/2023 Approved RYAN SALAZAR
Green Building Rough 12/8/2023 Approved RYAN SALAZAR
HVAC-Rough 12/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/8/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 12/8/2023 Approved RYAN SALAZAR
Insulation 12/13/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/13/2023 Approved RYAN SALAZAR
Shower Pan 12/13/2023 Approved RYAN SALAZAR
Drywall Nailing 12/18/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/29/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/29/2024 Corrections Issued JENNIFER RABUCHIN
Final 1/29/2024 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 1/29/2024 Approved JENNIFER RABUCHIN
Gas Test 1/29/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/29/2024 Approved JENNIFER RABUCHIN
HVAC-Final 1/29/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/29/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 1/29/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 1/29/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/31/2024 Approved RYAN SALAZAR
Final 1/31/2024 OK to Issue CofO RYAN SALAZAR
Gas Test 1/31/2024 Approved RYAN SALAZAR
HVAC-Final 1/31/2024 Approved RYAN SALAZAR
PLUMBING-Final 1/31/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 1/31/2024 Approved RYAN SALAZAR