12240-12242 W LULL ST 91605
Certificate Information: 12240-12242 W LULL ST 91605
- Application / Permit
- 23014-20000-02347
- Plan Check / Job No.
- B23VN07762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 16'9" X 28'3" ADDITION ATTACHED TO (E) SINGLE FAMILY DWELLING TO BECOME A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (e). WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/23/2023
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | MADISON ODELL |
| Corrections Issued | 6/17/2023 | MADISON ODELL |
| Plan Check Approved | 9/21/2023 | MADISON ODELL |
| Issued | 9/23/2023 | APPLICANT |
| CofO in Progress | 6/26/2024 | MATTHEW NELSON |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
| CofO Issued | 7/3/2024 | RUBEN SALAS |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 7/3/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 8/15/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 9/18/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/18/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 11/20/2023 | Corrections Issued | WILLIAM WREN |
| Deputy Drilled-In Anchors | 11/22/2023 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 11/28/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 11/28/2023 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 12/4/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/9/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/9/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/9/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 1/11/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/25/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 1/25/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 1/25/2024 | Approved | MATTHEW NELSON |
| Insulation | 2/7/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 2/22/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/19/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 3/19/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 3/28/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/29/2024 | Approved | MATTHEW NELSON |
| Final | 5/15/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/15/2024 | Approved | MATTHEW NELSON |
| Final | 6/25/2024 | OK to Issue CofO | MATTHEW NELSON |