3021 W DEL MONTE DR 90026
Certificate Information: 3021 W DEL MONTE DR 90026
- Application / Permit
- 23014-20000-02340
- Plan Check / Job No.
- B23VN07734
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODE, 22'-0" X 18'-0" & 8'-0" X 26'-6" ADDITION TO (E) SFD PER ENGINEERING. FIRE SPRINKLER REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/17/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/22/2023 | APPLICANT |
| Plan Check Approved | 8/31/2023 | JESSE ARELLANO |
| Issued | 10/20/2023 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 7/10/2023 | DAVID URITA |
| Low Impact Development (LID) | Cleared | 8/18/2023 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | JEANIE LAM |
| Sewer availability | Cleared | 8/23/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/31/2023 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/2/2023 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 11/6/2023 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 11/6/2023 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 11/6/2023 | Approved | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 4/8/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/21/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 5/21/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 5/21/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/21/2024 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 5/21/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 6/14/2024 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/14/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 6/14/2024 | Approved | JEFFREY MEAD |
| Insulation | 6/18/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/21/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 6/21/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | FREDDIE RIVERA |
| Insulation | 6/28/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 7/8/2024 | Approved | FREDDIE RIVERA |
| Shower Pan | 9/24/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 9/26/2024 | Approved | ANTHONY RAMOS |
| Final | 10/29/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/29/2024 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/29/2024 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/17/2024 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 11/17/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 11/17/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 1/8/2026 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | FREDDIE RIVERA |
| Special/Order Compliance | 3/9/2026 | Corrections Issued | FREDDIE RIVERA |
| Final | 3/31/2026 | Corrections Issued | FREDDIE RIVERA |