3021 W DEL MONTE DR 90026

Certificate Information: 3021 W DEL MONTE DR 90026

Application / Permit
23014-20000-02340
Plan Check / Job No.
B23VN07734
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODE, 22'-0" X 18'-0" & 8'-0" X 26'-6" ADDITION TO (E) SFD PER ENGINEERING. FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 10/20/2023
Issuing Office
Valley
Current Status
Issued on 10/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 ARTIN ZARUKIAN
Corrections Issued 6/17/2023 ARTIN ZARUKIAN
Building Plans Picked Up 6/22/2023 APPLICANT
Plan Check Approved 8/31/2023 JESSE ARELLANO
Issued 10/20/2023 APPLICANT

Permit Application Clearance Information

ZI Cleared 7/10/2023 DAVID URITA
Low Impact Development (LID) Cleared 8/18/2023 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 8/23/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 8/23/2023 JEANIE LAM
Sewer availability Cleared 8/23/2023 JEANIE LAM
Grading Pre-Inspection Cleared 8/31/2023 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/2/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 11/6/2023 Approved FREDDIE RIVERA
METHANE-Barrier 11/6/2023 Approved FREDDIE RIVERA
METHANE-Subgrade 11/6/2023 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 4/8/2024 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 5/21/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval FREDDIE RIVERA
Green Building Rough 5/21/2024 Partial Inspection FREDDIE RIVERA
METHANE-Rough 5/21/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 5/21/2024 Corrections Issued FREDDIE RIVERA
Wood Frame 5/21/2024 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/14/2024 Corrections Issued JEFFREY MEAD
Interior/Exterior Lathing 6/14/2024 Partial Approval JEFFREY MEAD
PLUMBING-Rough 6/14/2024 Approved JEFFREY MEAD
Insulation 6/18/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 6/21/2024 Corrections Issued FREDDIE RIVERA
Green Building Rough 6/21/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/28/2024 Approved FREDDIE RIVERA
Insulation 6/28/2024 Approved FREDDIE RIVERA
Drywall Nailing 7/8/2024 Approved FREDDIE RIVERA
Shower Pan 9/24/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 9/26/2024 Approved ANTHONY RAMOS
Final 10/29/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 10/29/2024 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 10/29/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 12/17/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Not Ready FREDDIE RIVERA
Final 11/17/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 11/17/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Not Ready FREDDIE RIVERA
Final 1/8/2026 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved FREDDIE RIVERA
Special/Order Compliance 3/9/2026 Corrections Issued FREDDIE RIVERA
Final 3/31/2026 Corrections Issued FREDDIE RIVERA