8213 N LAURELGROVE AVE 91605

Certificate Information: 8213 N LAURELGROVE AVE 91605

Application / Permit
23014-20000-02338
Plan Check / Job No.
B23VN07721
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
49'-0" X 29'-5" ADDITION TO (E) DETACHED GARAGE FOR NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 ARTIN ZARUKIAN
Corrections Issued 6/17/2023 ARTIN ZARUKIAN
Plan Check Approved 11/13/2023 ANGELICA MARTINEZ
Issued 1/10/2024 APPLICANT
CofO in Progress 7/24/2024 MATTHEW NELSON
Permit Finaled 7/26/2024 RUBEN SALAS
CofO Issued 7/26/2024 RUBEN SALAS
Permit Finaled 7/26/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/30/2023 TAL SHEMEN
Sewer availability Cleared 6/30/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 7/14/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/14/2023 TAL SHEMEN
Public Works-Highway Ded. Cleared 7/14/2023 TAL SHEMEN
Public Works-Open Permits Cleared 7/14/2023 TAL SHEMEN
Public Works-Sewers Cleared 7/14/2023 TAL SHEMEN
Construction near power lines Cleared 11/4/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/23/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/23/2024 Approved CHRISTOPHER ROJAS
Pre-Inspection 1/23/2024 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/13/2024 Partial Approval MATTHEW NELSON
PLUMBING-Rough 2/13/2024 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready MATTHEW NELSON
Underground Mechanical 2/13/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 3/18/2024 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 3/18/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval MATTHEW NELSON
Green Building Rough 3/18/2024 Not Ready for Inspection MATTHEW NELSON
Wood Frame 3/18/2024 Partial Approval MATTHEW NELSON
HVAC-Rough 3/29/2024 Approved MATTHEW NELSON
PLUMBING-Rough 3/29/2024 Approved MATTHEW NELSON
Underground Mechanical 3/29/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/2/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/2/2024 Approved MATTHEW NELSON
Green Building Rough 4/2/2024 Approved MATTHEW NELSON
Wood Frame 4/2/2024 Approved MATTHEW NELSON
Insulation 4/5/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/5/2024 Approved MATTHEW NELSON
Drywall Nailing 4/11/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/11/2024 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready WILLIAM WREN
ELECTRICAL-Final 7/1/2024 Approved MATTHEW NELSON
Final 7/1/2024 Corrections Issued MATTHEW NELSON
Green Building Final 7/1/2024 Approved MATTHEW NELSON
HVAC-Final 7/1/2024 Approved MATTHEW NELSON
PLUMBING-Final 7/1/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 7/1/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 7/1/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 7/23/2024 Approved MATTHEW NELSON
Final 7/23/2024 OK to Issue CofO MATTHEW NELSON
Gas Test 7/23/2024 Approved MATTHEW NELSON
HVAC-Final 7/23/2024 Approved MATTHEW NELSON
PLUMBING-Final 7/23/2024 Approved MATTHEW NELSON