6426 N GREENBUSH AVE 91401
Certificate Information: 6426 N GREENBUSH AVE 91401
- Application / Permit
- 23014-20000-02335
- Plan Check / Job No.
- B23VN07715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 37'-3" X 43'-4" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - FIRE SPRINKLER REQUIRED THROUGHOUT - PER WFPP
- Permit Issued
- Issued on 10/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/17/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Plan Check Approved | 8/4/2023 | DANIEL ABRAMYAN |
| Issued | 10/5/2023 | APPLICANT |
| CofO in Progress | 6/29/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
| CofO Issued | 7/23/2024 | RUBEN SALAS |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/13/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 7/25/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/1/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/22/2023 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 11/30/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/4/2023 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/5/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 12/8/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 1/4/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/8/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 1/26/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Order to Comply Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/13/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/13/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/13/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 2/15/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/15/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 2/26/2024 | Not Ready for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 2/26/2024 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 3/4/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/4/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 3/4/2024 | Partial Approval | JOSE AVILA |
| Insulation | 3/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/18/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/12/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 6/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 6/10/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Pre-Inspection | 6/13/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Final | 6/28/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | OGANES TARAKHCHYAN |