11025 W EMELITA ST 91601
Certificate Information: 11025 W EMELITA ST 91601
- Application / Permit
- 23014-20000-02320
- Plan Check / Job No.
- B23VN07673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE WITH 14'-0" X 16'-0" ADDITION INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). AND 32'-1" X 8-'2" PATIO COVER ADDITION. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 06/02/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/19/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 6/17/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 6/22/2023 | APPLICANT |
| Plan Check Approved | 7/18/2023 | ALEC MOUSAKHANIAN |
| Issued | 7/19/2023 | APPLICANT |
| CofO in Progress | 4/18/2024 | SCOTT SHUSTER |
| Permit Finaled | 6/3/2024 | DAVID JAMES |
| CofO Issued | 6/3/2024 | DAVID JAMES |
| Permit Finaled | 6/3/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 7/3/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 7/14/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/25/2023 | Corrections Issued | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 8/9/2023 | Approved | SCOTT SHUSTER |
| Footing/Foundation/Slab | 8/9/2023 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 8/14/2023 | Partial Approval | BRYAN MEYER |
| Wood Frame | 8/29/2023 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 12/5/2023 | Partial Approval | SCOTT SHUSTER |
| Underground Mechanical | 12/5/2023 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 12/12/2023 | Approved | SCOTT SHUSTER |
| Underground Mechanical | 12/12/2023 | Partial Inspection | SCOTT SHUSTER |
| Underground Mechanical | 12/13/2023 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 12/29/2023 | Partial Inspection | SCOTT SHUSTER |
| ELECTRICAL-Rough | 12/29/2023 | Partial Inspection | SCOTT SHUSTER |
| Green Building Rough | 12/29/2023 | Partial Approval | SCOTT SHUSTER |
| HVAC-Rough | 12/29/2023 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Rough | 12/29/2023 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 1/3/2024 | Corrections Issued | SCOTT SHUSTER |
| ELECTRICAL-Rough | 1/3/2024 | Approved | SCOTT SHUSTER |
| Green Building Rough | 1/3/2024 | Approved | SCOTT SHUSTER |
| HVAC-Rough | 1/3/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Rough | 1/3/2024 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 1/16/2024 | Approved | THOMAS WOODS |
| Insulation | 1/16/2024 | Not Ready for Inspection | THOMAS WOODS |
| Shower Pan | 1/16/2024 | Approved | THOMAS WOODS |
| Insulation | 1/22/2024 | Partial Approval | SCOTT SHUSTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Approval | SCOTT SHUSTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Approved | THOMAS WOODS |
| Insulation | 2/13/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 2/13/2024 | Approved | THOMAS WOODS |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | THOMAS WOODS |
| Special/Order Compliance | 2/14/2024 | Partial Inspection | SCOTT SHUSTER |
| Drywall Nailing | 2/21/2024 | Approved | SCOTT SHUSTER |
| Special/Order Compliance | 3/19/2024 | Partial Approval | SCOTT SHUSTER |
| ELECTRICAL-Final | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| Final | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 4/2/2024 | Approved | SCOTT SHUSTER |
| HVAC-Final | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Final | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | SCOTT SHUSTER |
| Service/Power Release | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| Smoke Detectors | 4/2/2024 | Partial Inspection | SCOTT SHUSTER |
| Final | 4/5/2024 | Partial Inspection | SCOTT SHUSTER |
| HVAC-Final | 4/5/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Final | 4/5/2024 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | SCOTT SHUSTER |
| Smoke Detectors | 4/5/2024 | Approved | SCOTT SHUSTER |
| Final | 4/9/2024 | Partial Approval | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | SCOTT SHUSTER |
| ELECTRICAL-Final | 4/18/2024 | Approved | SCOTT SHUSTER |
| Final | 4/18/2024 | OK to Issue CofO | SCOTT SHUSTER |