14977 W PADDOCK ST 91342

Certificate Information: 14977 W PADDOCK ST 91342

Application / Permit
23014-20000-02311
Plan Check / Job No.
B23VN07652
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan SB9 SINGLE FAMILY ADDITION (per sb9 two unit development), ATTACHED TO (E) GARAGE WITH (N) ATTACHED CARPORT. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 ADRIANA LOPEZ
Corrections Issued 7/12/2023 ADRIANA LOPEZ
Quality Review Completed 7/21/2023 FARUK SEZER
Applicant returned to address corrections 3/14/2024 ADRIANA LOPEZ
Plan Check Approved 4/2/2024 ADRIANA LOPEZ
Issued 4/3/2024 APPLICANT
CofO in Progress 10/25/2024 JENNIFER RABUCHIN
CofO in Progress 10/30/2024 ROBERT GOLD
CofO in Progress 11/26/2024 JENNIFER RABUCHIN
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 8/21/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 8/21/2023 NELSON RODRIGUEZ
Grading Pre-Inspection Cleared 8/29/2023 MICHAEL TEMPLE
Address approval Cleared 8/30/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/1/2023 MEGAN GODINEZ
Sewer availability Cleared 9/1/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 12/1/2023 GILBERT URREA
Construction near power lines Cleared 12/29/2023 TINA MIRANDA
Construction within easement Cleared 12/29/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 1/25/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 1/25/2024 CARLOS AGUILERA
Senate Bill 9 Cleared 1/30/2024 NELSON RODRIGUEZ
GPI Written Notices Cleared 3/14/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/30/2024 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/1/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/8/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/8/2024 Conditional Approval ROBERT GOLD
Sewer 5/8/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 5/8/2024 Partial Approval JENNIFER RABUCHIN
Insulation 5/13/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/13/2024 Partial Approval JENNIFER RABUCHIN
Deck 5/15/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval MATTHEW NELSON
Deputy Wood Construction 6/4/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 7/1/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Approved JENNIFER RABUCHIN
Green Building Rough 7/1/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/1/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/1/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/1/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/11/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/11/2024 Approved JENNIFER RABUCHIN
Green Building Rough 7/11/2024 Approved JENNIFER RABUCHIN
Insulation 7/11/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/11/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 7/29/2024 Approved LOUIS ESCOTO
Underground Mechanical 8/21/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/4/2024 Corrections Issued JENNIFER RABUCHIN
Final 10/4/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/4/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/4/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/4/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 10/4/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/9/2024 Approved JENNIFER RABUCHIN
Final 10/9/2024 Partial Approval JENNIFER RABUCHIN
HVAC-Final 10/9/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/9/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 10/9/2024 Approved JENNIFER RABUCHIN
Final 10/25/2024 OK to Issue CofO JENNIFER RABUCHIN
Special/Order Compliance 10/28/2024 Corrections Issued JENNIFER RABUCHIN