14977 W PADDOCK ST 91342
Certificate Information: 14977 W PADDOCK ST 91342
- Application / Permit
- 23014-20000-02311
- Plan Check / Job No.
- B23VN07652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan SB9 SINGLE FAMILY ADDITION (per sb9 two unit development), ATTACHED TO (E) GARAGE WITH (N) ATTACHED CARPORT. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
- Permit Issued
- Issued on 4/3/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | ADRIANA LOPEZ |
| Corrections Issued | 7/12/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 7/21/2023 | FARUK SEZER |
| Applicant returned to address corrections | 3/14/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 4/2/2024 | ADRIANA LOPEZ |
| Issued | 4/3/2024 | APPLICANT |
| CofO in Progress | 10/25/2024 | JENNIFER RABUCHIN |
| CofO in Progress | 10/30/2024 | ROBERT GOLD |
| CofO in Progress | 11/26/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/21/2023 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 8/21/2023 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 8/29/2023 | MICHAEL TEMPLE |
| Address approval | Cleared | 8/30/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/1/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 12/1/2023 | GILBERT URREA |
| Construction near power lines | Cleared | 12/29/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 12/29/2023 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 1/25/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 1/30/2024 | NELSON RODRIGUEZ |
| GPI Written Notices | Cleared | 3/14/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/30/2024 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 5/1/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/8/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 5/8/2024 | Conditional Approval | ROBERT GOLD |
| Sewer | 5/8/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 5/8/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deck | 5/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 6/4/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 7/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/1/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/1/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 7/1/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/29/2024 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 8/21/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/4/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/4/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/4/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 10/4/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 10/9/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/9/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/25/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/28/2024 | Corrections Issued | JENNIFER RABUCHIN |