10336-10338 N MEMORY PARK AVE 91345

Certificate Information: 10336-10338 N MEMORY PARK AVE 91345

Application / Permit
23014-20000-02307
Plan Check / Job No.
B23VN07624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED 2-CAR GARAGE (346 SQFT) INTO ADU W/171 SQFT ADDITION. PER LAMC 12.22 A.33(c)(e) ADD AN ATTACHED COVERED PATIO COVER AT REAR (105 SQFT) W/FRONT COVERED PORCH (41 SQFT). INTERIOR REMODEL TO EXISTING BATHROOMS/BEDROOMS AND WINDOWS THROUGHOUT.
Permit Issued
Issued on 7/24/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 PETER MOSESIAN
Corrections Issued 6/18/2023 PETER MOSESIAN
Quality Review Completed 6/21/2023 OMID HEDAYAT
Plan Check Approved 7/5/2023 PETER MOSESIAN
Issued 7/24/2023 APPLICANT
CofO in Progress 4/24/2024 JENNIFER RABUCHIN
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/26/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/26/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/28/2023 JOHN LIN
Sewer availability Cleared 6/28/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/2/2023 Corrections Issued MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 10/10/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/19/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/19/2023 Partial Approval JENNIFER RABUCHIN
Insulation 10/30/2023 Corrections Issued KEVIN BERBERYAN
Insulation 11/2/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 11/16/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/14/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/21/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 12/21/2023 Approved JOHN COLEMAN
HVAC-Rough 12/21/2023 Approved JOHN COLEMAN
PLUMBING-Rough 12/21/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 12/28/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/28/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/28/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 1/3/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/3/2024 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 1/5/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/17/2024 Approved KEVIN BERBERYAN
Final 4/17/2024 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 4/17/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 4/17/2024 Approved KEVIN BERBERYAN
Smoke Detectors 4/17/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/24/2024 Approved JENNIFER RABUCHIN
Final 4/24/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/24/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/24/2024 Approved JENNIFER RABUCHIN
Service/Power Release 4/24/2024 Not Required JENNIFER RABUCHIN