332 S HIGHLAND AVE 90036

Certificate Information: 332 S HIGHLAND AVE 90036

Application / Permit
23014-20000-02285
Plan Check / Job No.
B23VN07587
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) 25'-5" X 21'-11" 1ST AND 2ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING "COMPLY WITH DEPARTMENT ORDER effective date 01/04/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/4/2023
Issuing Office
Valley
Current Status
Issued on 12/4/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/6/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/6/2023 OMID HEDAYAT
Building Plans Picked Up 7/10/2023 APPLICANT
Plan Check Approved 11/20/2023 SEWADA ZADOORAN MILAGARDI
Issued 12/4/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2023 JOSEPH RHYU
Sewer availability Cleared 7/22/2023 JOSEPH RHYU
City Hist. Cultural Monument Cleared 9/26/2023 SUKI GERSHENHORN
HPOZ Cleared 9/26/2023 SUKI GERSHENHORN
Historic monument Cleared 9/26/2023 SUKI GERSHENHORN
ZI Cleared 9/26/2023 SUKI GERSHENHORN
Low Impact Development (LID) Cleared 10/18/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/24/2023 DAVID LOPEZ
Hold Cleared 1/24/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/30/2024 Approved PETER RUBIO
Deputy Drilled-In Anchors 2/14/2024 Approved PETER RUBIO
Footing/Foundation/Slab 2/14/2024 Approved PETER RUBIO
METHANE-Barrier 2/14/2024 Approved PETER RUBIO
METHANE-Subgrade 2/14/2024 Approved PETER RUBIO
HVAC-Rough 2/22/2024 Approved PETER RUBIO
PLUMBING-Rough 2/22/2024 Approved PETER RUBIO
BUILDING-Rough-Frame 3/7/2024 Not Ready for Inspection PETER RUBIO
ELECTRICAL-Rough 3/7/2024 Not Ready for Inspection PETER RUBIO
Green Building Rough 3/7/2024 Not Ready for Inspection PETER RUBIO
METHANE-Rough 3/7/2024 Approved PETER RUBIO
Wood Frame 3/7/2024 Not Ready for Inspection PETER RUBIO
Wood Frame 3/21/2024 Partial Approval PETER RUBIO
Interior/Exterior Lathing 4/4/2024 Partial Inspection RUBEN PEREZ
ELECTRICAL-Rough 4/22/2024 Approved PETER RUBIO
Insulation 4/22/2024 Not Ready for Inspection PETER RUBIO
Wood Frame 4/22/2024 Not Ready for Inspection PETER RUBIO
BUILDING-Rough-Frame 4/30/2024 No Access for Inspection PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 No Access for Inspection PETER RUBIO
Green Building Rough 4/30/2024 No Access for Inspection PETER RUBIO
Insulation 4/30/2024 No Access for Inspection PETER RUBIO
Interior/Exterior Lathing 4/30/2024 No Access for Inspection PETER RUBIO
Shower Pan 4/30/2024 No Access for Inspection PETER RUBIO
BUILDING-Rough-Frame 5/2/2024 Approved PETER RUBIO
Green Building Rough 5/2/2024 Approved PETER RUBIO
Insulation 5/2/2024 Approved PETER RUBIO
Interior/Exterior Lathing 5/2/2024 Approved PETER RUBIO
Shower Pan 5/2/2024 Approved PETER RUBIO
Drywall Nailing 5/9/2024 Not Ready for Inspection ROBERT NILES
Drywall Nailing 5/14/2024 Not Ready for Inspection RUBEN PEREZ
Drywall Nailing 5/23/2024 Not Ready for Inspection COREY HUPP