10134-10136 N FORBES AVE 91343

Certificate Information: 10134-10136 N FORBES AVE 91343

Application / Permit
23014-20000-02276
Plan Check / Job No.
B23VN07562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ADDITION FOR NEW LAUNDRY ROOM.
Permit Issued
Issued on 7/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/13/2023 JEROME MAGAT PALMA
Corrections Issued 6/14/2023 JEROME MAGAT PALMA
Building Plans Picked Up 6/26/2023 APPLICANT
Plan Check Approved 7/21/2023 ROSENDO MEDINA
Issued 7/21/2023 APPLICANT
CofO in Progress 6/26/2024 JAVIER RAMOS JR
CofO Issued 8/15/2024 DANIEL ORRANTE
Permit Finaled 8/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/12/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/13/2023 LEE GUILBEAUX
Sewer availability Cleared 7/13/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/13/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 7/14/2023 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/13/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 11/21/2023 Partial Approval JAVIER RAMOS JR
Sewer 11/21/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 11/27/2023 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 12/6/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/20/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/10/2024 Partial Inspection JAVIER RAMOS JR
Green Building Rough 1/10/2024 Not Ready for Inspection JAVIER RAMOS JR
Shower Pan 1/10/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/30/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/30/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 1/30/2024 Partial Approval JAVIER RAMOS JR
Gas Test 1/30/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 1/30/2024 Approved JAVIER RAMOS JR
HVAC-Rough 1/30/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 1/30/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/30/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 2/9/2024 Partial Inspection JAVIER RAMOS JR
Gas Test 2/9/2024 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 2/9/2024 Approved JAVIER RAMOS JR
Gas Test 2/12/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 2/12/2024 Corrections Issued JAVIER RAMOS JR
Insulation 2/12/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/12/2024 Approved JAVIER RAMOS JR
Drywall Nailing 2/27/2024 Approved JOHN COLEMAN
ELECTRICAL-Final 5/9/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Final 5/9/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 6/11/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/11/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 6/11/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 6/11/2024 Approved JAVIER RAMOS JR
Green Building Final 6/11/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/11/2024 Partial Inspection JAVIER RAMOS JR
Insulation 6/11/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 6/11/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 6/14/2024 Partial Inspection JAVIER RAMOS JR
Final 6/14/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 6/14/2024 Partial Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/14/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 6/25/2024 Approved JAVIER RAMOS JR
Final 6/25/2024 OK to Issue CofO JAVIER RAMOS JR
Gas Test 6/25/2024 Approved JAVIER RAMOS JR
HVAC-Final 6/25/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 6/25/2024 Approved JAVIER RAMOS JR
Smoke Detectors 6/25/2024 Approved JAVIER RAMOS JR