19155 W HARLISS ST 91324

Certificate Information: 19155 W HARLISS ST 91324

Application / Permit
23014-20000-02256
Plan Check / Job No.
B23VN07460
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Remodel and Rear Addition to (E) Single Family Dwelling, Scope of Work to Include Enlargement of Master Bedroom and Bath, and Rebuild Rear Covered Patio
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
Issued on 6/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 EDWIN ESPIN
Corrections Issued 6/20/2023 EDWIN ESPIN
Applicant returned to address corrections 9/21/2023 DAVID CASTILLO
Plan Check Approved 9/26/2023 DAVID CASTILLO
Issued 9/28/2023 APPLICANT
CofO in Progress 1/12/2026 KRISTEN CAUSEY
CofO in Progress 1/27/2026 HENRY KIM
No Progress 6/30/2026 JACK KARGODORIAN

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/5/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/5/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/7/2023 CARLOS AGUILERA

Contact Information

Contractor Construction For Less; Lic. No.: 965043-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 10/4/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/11/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval JOHN KIDWELL
HVAC-Rough 11/22/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 12/8/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 2/20/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 2/20/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/27/2024 Approved KRISTEN CAUSEY
Green Building Rough 2/27/2024 Approved KRISTEN CAUSEY
Insulation 3/15/2024 Approved KRISTEN CAUSEY
Drywall Nailing 4/16/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/21/2024 Approved KRISTEN CAUSEY
Shower Pan 7/18/2024 Approved KRISTEN CAUSEY
Service/Power Release 7/26/2024 Partial Inspection KRISTEN CAUSEY
Final 12/29/2025 Not Ready for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 12/29/2025 Approved KRISTEN CAUSEY
Green Building Final 12/29/2025 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 12/29/2025 Approved KRISTEN CAUSEY
Final 1/8/2026 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 1/8/2026 Approved KRISTEN CAUSEY
Special/Order Compliance 1/27/2026 Corrections Issued HENRY KIM