8160 W LAURELMONT DR 90046
Certificate Information: 8160 W LAURELMONT DR 90046
- Application / Permit
- 23014-20000-02223
- Plan Check / Job No.
- B23VN07330
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND (E) DECK (10'-1"X 75'-4") ON PILES, ADD PATIO COVER (IRR 18'-4" X 8'-1") & OPEN TRELLIS (18'-8" X 15'-5") TO (E) SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/4/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/6/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/7/2023 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2023 | APPLICANT |
| Applicant returned to address corrections | 7/25/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/12/2023 | NILOOFAR MEHRAIN |
| Issued | 10/4/2023 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/25/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 8/25/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 8/28/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/31/2023 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 9/12/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/12/2023 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 9/12/2023 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2023 | Corrections Issued | STUART CHAPMAN |
| Piling/Pier/Caisson | 11/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Reinforced Concrete Frame | 11/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Reinf. Concrete | 11/13/2023 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/13/2023 | Partial Approval | STUART CHAPMAN |
| Piling/Pier/Caisson | 11/13/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 11/17/2023 | Conditional Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 1/10/2024 | Conditional Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Approved | ROY SPAULDING |
| Structural Steel Frame | 1/16/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 7/23/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 7/23/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 8/12/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/12/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/14/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 9/20/2024 | Approved | BRIAN SULLIVAN |
| Wood Frame | 9/20/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Not Ready | ROY SPAULDING |
| Final | 8/26/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 8/26/2025 | Approved | ROY SPAULDING |
| Green Building Final | 8/26/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 8/26/2025 | Approved | ROY SPAULDING |
| Final | 5/6/2026 | Corrections Issued | ROY SPAULDING |
| Final | 5/18/2026 | Corrections Issued | ROY SPAULDING |