9560 N NATICK AVE 91343

Certificate Information: 9560 N NATICK AVE 91343

Application / Permit
23014-20000-02204
Plan Check / Job No.
B23VN07279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
11'-0" X 18'-0" ADDITION AND CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER WFPP
Permit Issued
Issued on 4/9/2024
Issuing Office
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/2/2023 DANIEL ABRAMYAN
Corrections Issued 8/3/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 3/6/2024 DANIEL ABRAMYAN
Plan Check Approved 3/10/2024 DANIEL ABRAMYAN
Issued 4/9/2024 APPLICANT
CofO in Progress 7/18/2025 JENNIFER RABUCHIN
Permit Finaled 8/5/2025 RUBEN SALAS
CofO Issued 8/5/2025 RUBEN SALAS
Permit Finaled 8/5/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/15/2023 NIKKI ZULUETA
Construction near power lines Cleared 2/14/2024 RIDWAN HARDY
Construction within easement Cleared 2/14/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/23/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/23/2024 EDGAR ALCARAZ
Sewer availability Cleared 2/23/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/18/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/24/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/2/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 12/2/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/2/2024 Corrections Issued JENNIFER RABUCHIN
Sewer 12/2/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 12/2/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/9/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/9/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/9/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/12/2024 Partial Approval JENNIFER RABUCHIN
Insulation 12/23/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 1/2/2025 Approved JENNIFER RABUCHIN
Shower Pan 3/26/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 5/16/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/16/2025 Corrections Issued JENNIFER RABUCHIN
Final 5/16/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/16/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/16/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/7/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/7/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/21/2025 Approved JENNIFER RABUCHIN
Final 7/21/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/21/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/21/2025 Approved JENNIFER RABUCHIN