9560 N NATICK AVE 91343
Certificate Information: 9560 N NATICK AVE 91343
- Application / Permit
- 23014-20000-02204
- Plan Check / Job No.
- B23VN07279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 11'-0" X 18'-0" ADDITION AND CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER WFPP
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 8/3/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 3/6/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 3/10/2024 | DANIEL ABRAMYAN |
| Issued | 4/9/2024 | APPLICANT |
| CofO in Progress | 7/18/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 2/14/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/14/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/23/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/23/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/24/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 12/2/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 12/2/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 12/2/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/9/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/9/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/12/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 12/23/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/2/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/26/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 5/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 5/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/7/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/21/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |