1345 1/2 W 59TH ST 90044

Certificate Information: 1345 1/2 W 59TH ST 90044

Application / Permit
23014-20000-02196
Plan Check / Job No.
B23VN07241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 22' 6" X 29' ACCESSORY DWELLING UNIT TO REAR OF (E) SFD PER LAMC 12.22 A.33(c) AND (e). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2023 APPLICANT
Assigned to Plan Check Engineer 6/9/2023 SERGIO MUNIZ
Corrections Issued 6/12/2023 SERGIO MUNIZ
Building Plans Picked Up 6/14/2023 APPLICANT
Issued 7/31/2023 APPLICANT
CofO in Progress 9/20/2024 CRAIG DAVIS
No Progress 10/28/2024 CHARLES BOGHOSKHAN
CofO in Progress 10/28/2024 CHARLES BOGHOSKHAN
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/27/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/27/2023 WALLIE JONG
Sewer availability Cleared 6/27/2023 WALLIE JONG
Low Impact Development (LID) Cleared 7/12/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/14/2023 WALLIE JONG

Contact Information

Contractor Mg All Construction; Lic. No.: 1082580-B 20201 SHERMAN WAY STE 101B      WINNETKA, CA 91306

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/30/2023 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 9/1/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/18/2023 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 9/19/2023 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/29/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 2/29/2024 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Approved RONNIE MINDANAO
Green Building Rough 2/29/2024 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 2/29/2024 Approved RONNIE MINDANAO
Sewer 2/29/2024 Corrections Issued RONNIE MINDANAO
Shower Pan 2/29/2024 Approved RONNIE MINDANAO
ELECTRICAL-Rough 3/4/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 3/7/2024 Partial Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 3/7/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/12/2024 Approved DAVID FEILER
Green Building Rough 3/12/2024 Approved DAVID FEILER
Insulation 3/12/2024 Approved DAVID FEILER
Drywall Nailing 3/14/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 5/3/2024 Corrections Issued CRAIG DAVIS
Final 5/3/2024 Corrections Issued CRAIG DAVIS
Green Building Final 5/3/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 5/3/2024 Approved CRAIG DAVIS
PLUMBING-Final 5/3/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved CRAIG DAVIS
Smoke Detectors 5/3/2024 Approved CRAIG DAVIS
Final 5/14/2024 Partial Inspection CRAIG DAVIS
Green Building Final 5/14/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 9/19/2024 Approved CRAIG DAVIS
Final 9/19/2024 OK to Issue CofO CRAIG DAVIS
PLUMBING-Final 9/19/2024 Approved CRAIG DAVIS
Service/Power Release 10/22/2024 Approved CRAIG DAVIS