5432 N MORELLA AVE 91607
Certificate Information: 5432 N MORELLA AVE 91607
- Application / Permit
- 23014-20000-02193
- Plan Check / Job No.
- B23VN07231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF NEW BEDROOM TO THE (E) SFD.
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 12/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/2/2023 | MOHAMMAD ESMAILI |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 11/14/2023 | JOHN COLEMAN |
| Permit Finaled | 12/1/2023 | RUBEN SALAS |
| CofO Issued | 12/1/2023 | RUBEN SALAS |
| Permit Finaled | 12/1/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/5/2023 | JOANNA MARROQUIN |
| Roof/Waste drainage to street | Cleared | 6/10/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/12/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/1/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| Insulation | 9/15/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 9/15/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/25/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/25/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | JOHN COLEMAN |
| Final | 10/31/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 10/31/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 10/31/2023 | Approved | JOHN COLEMAN |
| MERV13>=Final | 10/31/2023 | Approved | JOHN COLEMAN |
| MERV13>=Rough | 10/31/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 10/31/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/6/2023 | Approved | MICHEL ABAJAN |
| Final | 11/8/2023 | OK to Issue CofO | JOHN COLEMAN |