17345 W CHATSWORTH ST 91344
Certificate Information: 17345 W CHATSWORTH ST 91344
- Application / Permit
- 23014-20000-02189
- Plan Check / Job No.
- B23VN07226
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- epLan: Convert and add 1255 s.f. to 1749 s.f. (E) House and 421 s.f. (E) detached garage to a 3425 s.f. child care facility per case no. ***ZA-2023-3923-CU*** *** Hours of operation from 8:00 a.m. to 6:00 p.m., Monday through Friday; Max enrollment 60 children; up to 6 years of age***
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- Issued on 12/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | KESETE HAREGOT |
| Corrections Issued | 7/12/2023 | KESETE HAREGOT |
| Quality Review Completed | 7/18/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 9/16/2024 | KESETE HAREGOT |
| Applicant returned to address corrections | 9/30/2024 | KESETE HAREGOT |
| Plan Check Approved | 12/24/2024 | KESETE HAREGOT |
| Plan Check Approved | 12/26/2024 | KESETE HAREGOT |
| Issued | 12/27/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/22/2023 | LEE GUILBEAUX |
| Green Code | Cleared | 2/25/2024 | MICHAEL AYERS |
| Sewer availability | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 5/9/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/10/2024 | KURT CORRAL |
| DAS Clearance | Cleared | 5/21/2024 | Ricardo Ramirez Solis |
| Fire Marshal Fire Life Safety | Cleared | 6/4/2024 | FIRE DEPARTMENT |
| Low Impact Development (LID) | Cleared | 6/12/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/12/2024 | LEE GUILBEAUX |
| Frnt yard landscape/Water mgmt | Cleared | 7/15/2024 | DAVID URITA |
| Specific Plan | Cleared | 7/15/2024 | DAVID URITA |
| ZA Case | Cleared | 7/15/2024 | DAVID URITA |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 3/6/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Not Ready for Inspection | GREGORY POMISH |
| Special/Order Compliance | 7/18/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 10/30/2025 | Conditional Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/3/2025 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/4/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 1/13/2026 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Insulation | 1/15/2026 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Not Ready for Inspection | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 4/10/2026 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 4/23/2026 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/23/2026 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 4/27/2026 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 5/6/2026 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 6/23/2026 | Approved | EDWIN GREGORYONA |
| Wood Frame | 6/23/2026 | Partial Inspection | EDWIN GREGORYONA |
| Insulation | 7/2/2026 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 7/9/2026 | Approved | EDWIN GREGORYONA |