13700 N ELDRIDGE AVE 91342

Certificate Information: 13700 N ELDRIDGE AVE 91342

Application / Permit
23014-20000-02185
Plan Check / Job No.
B23VN07204
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ADDITION (425 SF) TO (E) SFD
Permit Issued
Issued on 7/21/2023
Issuing Office
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2023 APPLICANT
Assigned to Plan Check Engineer 6/2/2023 JOHNPAUL ISIP
Corrections Issued 6/8/2023 JOHNPAUL ISIP
Plan Check Approved 7/13/2023 JOHNPAUL ISIP
Issued 7/21/2023 APPLICANT
CofO in Progress 4/18/2024 KEVIN BERBERYAN
Permit Finaled 9/12/2024 DANIEL ORRANTE
CofO Issued 9/12/2024 DANIEL ORRANTE
Permit Finaled 9/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/21/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 6/22/2023 FERNANDO GIL
Sewer availability Cleared 6/22/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/20/2023 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/26/2023 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/26/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/26/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/16/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/16/2024 Approved MICHEL ABAJAN
Green Building Rough 2/16/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/16/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 2/16/2024 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 2/21/2024 Partial Approval CRAIG DAVIS
PLUMBING-Rough 2/21/2024 Partial Approval CRAIG DAVIS
PLUMBING-Rough 2/26/2024 Approved MICHEL ABAJAN
Shower Pan 2/26/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/29/2024 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 2/29/2024 Approved KEVIN BERBERYAN
Insulation 3/4/2024 Conditional Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 3/4/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 3/7/2024 Approved KEVIN BERBERYAN
Final 4/11/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/11/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 4/11/2024 Approved KEVIN BERBERYAN
Final 4/16/2024 OK to Issue CofO KEVIN BERBERYAN