10421 W WEDDINGTON ST 91601
Certificate Information: 10421 W WEDDINGTON ST 91601
- Application / Permit
- 23014-20000-02182
- Plan Check / Job No.
- B23VN07199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Addition and Major Remodel to existing 1-story Single Family Dwelling, only 7' 11" of exterior wall and foundation to remain on North East portion of Lot. Rebuilt as 1-story (45' x 81' Irregular Shape) Single Family Dwelling, attached garage and attached patio cover in the back. NFPA 13D Fire Sprinklers Throughout. All work done per engineer.
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | NAREG ATARIAN |
| Corrections Issued | 6/21/2023 | NAREG ATARIAN |
| Quality Review Completed | 6/28/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/12/2023 | NAREG ATARIAN |
| Applicant returned to address corrections | 12/21/2023 | NAREG ATARIAN |
| Plan Check Approved | 1/19/2024 | NAREG ATARIAN |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 12/11/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 12/19/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/15/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 1/2/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/9/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2024 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 3/21/2024 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 3/28/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/29/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/3/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 5/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/28/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/29/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/12/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/12/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 6/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/24/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 9/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 9/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/4/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 10/8/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 10/8/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/11/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |