13517 W DELANO ST 91401

Certificate Information: 13517 W DELANO ST 91401

Application / Permit
23014-20000-02178
Plan Check / Job No.
B23VN07193
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 1. COMPLETE REMODEL AND ADDITION TO EXISTING S.F.D. CONVERTING 3 BEDROOM + TWO BATHROOMS INTO NEW 4 BEDROOMS + 3 BATHROOMS. 2. COMPLETE REMOVE EXISTING ROOF. 3. ROTATE GARAGE DOOR FROM SIDE ENTRY TO FRONT ENTRY, AND RELOCATE DRIVEWAY. NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 10/20/2023
Issuing Office
Current Status
CofO Issued on 10/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 NGHI SU
Corrections Issued 6/23/2023 NGHI SU
Quality Review Completed 6/29/2023 TU HUA
Applicant returned to address corrections 9/13/2023 NGHI SU
Plan Check Approved 10/19/2023 NGHI SU
Issued 10/20/2023 APPLICANT
CofO in Progress 8/13/2024 OGANES TARAKHCHYAN
Permit Finaled 10/21/2024 DANIEL ORRANTE
CofO Issued 10/21/2024 DANIEL ORRANTE
Permit Finaled 10/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/24/2023 NIKKI ZULUETA
Sewer availability Cleared 7/25/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 8/21/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/22/2023 ROMAN GUTIERREZ
Permit Cleared 9/7/2023 DAGOVERTO GUERRERO
Trees in Parkway Cleared 9/7/2023 ADALBERTO VERA

Contact Information

Contractor 1 Stop Builders; Lic. No.: 1033108-B       ,
Contractor K O B Remodeling Inc; Lic. No.: 1033108-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2023 Partial Inspection KIRK SANDERS
Excavation/Setback/Form/Re-Bar 12/7/2023 Approved JOSE AVILA
Footing/Foundation/Slab 12/7/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/8/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 12/15/2023 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 12/15/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Conditional Approval KIRK SANDERS
Green Building Rough 12/18/2023 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 12/18/2023 Not Ready for Inspection KIRK SANDERS
Deputy Drilled-In Anchors 12/29/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/29/2023 Approved JOSE AVILA
PLUMBING-Rough 12/29/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval KIRK SANDERS
Deputy Wood Construction 2/2/2024 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 2/23/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/23/2024 Partial Approval JOSE AVILA
HVAC-Rough 2/29/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/12/2024 Conditional Approval JOSE AVILA
Green Building Rough 3/12/2024 Approved JOSE AVILA
HVAC-Rough 3/12/2024 Approved JOSE AVILA
Interior/Exterior Lathing 3/12/2024 Approved JOSE AVILA
PLUMBING-Rough 3/12/2024 Approved JOSE AVILA
ELECTRICAL-Final 3/22/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 3/22/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 3/28/2024 Approved JOSE AVILA
ELECTRICAL-Rough 3/28/2024 Approved JOSE AVILA
Insulation 3/28/2024 Approved JOSE AVILA
Drywall Nailing 4/2/2024 Partial Inspection JOSE AVILA
Special/Order Compliance 4/2/2024 Corrections Issued JOSE AVILA
Pre-Inspection 5/10/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/12/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 6/12/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 7/26/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 7/31/2024 Approved OGANES TARAKHCHYAN
Final 7/31/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 7/31/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 7/31/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/31/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 7/31/2024 Approved OGANES TARAKHCHYAN
Final 8/7/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 8/12/2024 OK to Issue CofO OGANES TARAKHCHYAN