4749 N HALBRENT AVE 91403

Certificate Information: 4749 N HALBRENT AVE 91403

Application / Permit
23014-20000-02149
Plan Check / Job No.
B23VN07103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 11'-6" X 5'-5" ADDITION PER ENGINEERING & 16'-0" X 8'-6" PATIO ENCLOSURE ADDITION (PER ESR2676P) TO (E) SFD.
Permit Issued
Issued on 9/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2023 APPLICANT
Assigned to Plan Check Engineer 6/5/2023 ARTIN ZARUKIAN
Corrections Issued 6/5/2023 ARTIN ZARUKIAN
Building Plans Picked Up 6/7/2023 APPLICANT
Plan Check Approved 6/22/2023 ISIS ARGUETA
Issued 9/20/2023 APPLICANT
CofO in Progress 9/18/2024 JACK KARGODORIAN
Permit Finaled 9/25/2024 DANIEL ORRANTE
CofO Issued 9/25/2024 DANIEL ORRANTE
Permit Finaled 9/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/10/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/12/2023 CARLOS AGUILERA

Contact Information

Contractor Phan Jimmy; Lic. No.: 983407-B 1001 CHESWICK DRIVE      SAN JOSE, CA 95121
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/10/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/10/2023 Not Ready for Inspection THOMAS FINNILA
Sewer 10/10/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 10/24/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/24/2023 Not Ready for Inspection MISAEL ESPARZA
Reinforced Concrete Frame 10/24/2023 Not Ready for Inspection MISAEL ESPARZA
Sewer 10/24/2023 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/30/2023 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 10/30/2023 Not Ready for Inspection THOMAS FINNILA
Sewer 10/30/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/9/2023 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 11/13/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 12/22/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 1/19/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 1/19/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 1/25/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 1/25/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 2/21/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/21/2024 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 2/21/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/1/2024 Corrections Issued THOMAS FINNILA
Wood Frame 4/1/2024 Corrections Issued THOMAS FINNILA
Insulation 4/4/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 4/4/2024 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 5/14/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 5/17/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 5/17/2024 Approved JACK KARGODORIAN
Service/Power Release 5/22/2024 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 6/25/2024 Conditional Approval DAVID MATSON
Drywall Nailing 8/9/2024 Approved JACK KARGODORIAN
Drywall Nailing 9/9/2024 Approved CHRISTOPHE COCHRAN
Pre-Inspection 9/9/2024 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/10/2024 Approved CHRISTOPHE COCHRAN
Final 9/10/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/10/2024 Approved CHRISTOPHE COCHRAN
Green Building Final 9/10/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 9/10/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/10/2024 Approved CHRISTOPHE COCHRAN
Final 9/13/2024 OK to Issue CofO JACK KARGODORIAN
Green Building Final 9/13/2024 Approved JACK KARGODORIAN