7044 W GREELEY ST 1-3 91042

Certificate Information: 7044 W GREELEY ST 1-3 91042

Application / Permit
23014-20000-02142
Plan Check / Job No.
B23VN07066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION OF A NEW 2-STORY 1,286 SF DUPLEX ATTACHED TO EXISTING SFD W/ NEW 2-STORY 962 SF ADU PER LAMC 12.22 A.33(c) AND (e) ATTACHED TO DUPLEX W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
CofO Issued on 6/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 PETER MOSESIAN
Corrections Issued 6/17/2023 PETER MOSESIAN
Quality Review Completed 6/22/2023 OMID HEDAYAT
Plan Check Approved 11/29/2023 PETER MOSESIAN
Issued 12/7/2023 APPLICANT
CofO in Progress 3/25/2026 NICHOLAS TROWBRIDGE
Permit Finaled 6/12/2026 RUBEN SALAS
CofO Issued 6/12/2026 RUBEN SALAS
Permit Finaled 6/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/26/2023 TAL SHEMEN
Frnt yard landscape/Water mgmt Cleared 6/28/2023 DALIA MOKAYED
Grading Pre-Inspection Cleared 7/5/2023 ROBERT HUGHES
Specific Plan Cleared 9/19/2023 ERICK MARCHENA
ZI Cleared 9/19/2023 ERICK MARCHENA
Low Impact Development (LID) Cleared 10/25/2023 TRISH PARAS
Eng Process Fee Ord 176,300 Cleared 11/6/2023 TAL SHEMEN
Sewer availability Cleared 11/6/2023 TAL SHEMEN
Hydrant and Access approval Cleared 11/8/2023 LAVEON RIDER
Roof/Waste drainage to street Cleared 11/13/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2024 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 1/24/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval WILLIAM WREN
Deputy Wood Construction 4/1/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 5/23/2025 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/23/2025 Approved RAUL OLAGI
HVAC-Rough 5/23/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/23/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/5/2025 Not Ready for Inspection WILLIAM WREN
Green Building Rough 8/5/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/25/2025 Approved WILLIAM WREN
Insulation 8/25/2025 Corrections Issued WILLIAM WREN
Drywall Nailing 9/16/2025 Approved DAVID ANDERSON
Shower Pan 10/14/2025 Approved WILLIAM WREN
Sewer 10/21/2025 Approved KEVIN BERBERYAN
Underground Mechanical 10/21/2025 Approved KEVIN BERBERYAN
Final 3/18/2026 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 3/18/2026 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 3/18/2026 Approved NICHOLAS TROWBRIDGE
Final 3/24/2026 OK to Issue CofO NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved NICHOLAS TROWBRIDGE