8542 N DE CELIS PL 91343

Certificate Information: 8542 N DE CELIS PL 91343

Application / Permit
23014-20000-02135
Plan Check / Job No.
B23VN07057
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 18'-7" X 25'-11" ADDITION TO THE (E) SINGLE FAMILY DWELLING TO ADD 2 NEW BEDROOMS AND 3 NEW BATHROOMS AND REMODEL ENTIRE HOUSE.
Permit Issued
Issued on 6/16/2023
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2023 APPLICANT
Assigned to Plan Check Engineer 5/30/2023 MADISON ODELL
Corrections Issued 5/30/2023 MADISON ODELL
Issued 6/16/2023 APPLICANT
CofO in Progress 11/6/2025 GAREN HAYRAPETYAN
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/31/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/16/2023 LEE GUILBEAUX
Sewer availability Cleared 6/16/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/16/2023 LEE GUILBEAUX
Public Works-Sewers Cleared 6/16/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/14/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/25/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 6/25/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/25/2024 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 7/5/2024 Partial Approval RAUL OLAGI
Shower Pan 7/5/2024 Approved RAUL OLAGI
Special/Order Compliance 7/5/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 8/5/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 8/5/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 8/5/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 8/5/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/5/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/16/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 8/16/2024 Approved RAUL OLAGI
Green Building Rough 8/16/2024 Approved RAUL OLAGI
HVAC-Rough 8/16/2024 Approved RAUL OLAGI
PLUMBING-Rough 8/16/2024 Approved RAUL OLAGI
Insulation 8/23/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 8/23/2024 Partial Approval RAUL OLAGI
Drywall Nailing 9/3/2024 Approved GAREN HAYRAPETYAN
Final 10/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 10/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Final 10/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 10/21/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 11/6/2025 Approved GAREN HAYRAPETYAN
Final 11/6/2025 OK to Issue CofO GAREN HAYRAPETYAN
Footing/Foundation/Slab 11/6/2025 Approved GAREN HAYRAPETYAN
Green Building Final 11/6/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 11/6/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 11/6/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Approved GAREN HAYRAPETYAN