451-451 1/2 W 47TH PL 90037

Certificate Information: 451-451 1/2 W 47TH PL 90037

Application / Permit
23014-20000-02121
Plan Check / Job No.
B23VN07015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) 46'-6" X 20'-6" FIRST AND SECOND STORY ADDITION TO (E) SINGLE FAMILY DWELLING TO CREATE (1) (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND (N) DECK ADDITION ON SECOND FLOOR ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/21/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/23/2023 OMID HEDAYAT
Building Plans Picked Up 6/26/2023 APPLICANT
Plan Check Approved 10/27/2023 SEWADA ZADOORAN MILAGARDI
Issued 10/27/2023 APPLICANT
CofO in Progress 3/11/2026 RAUL BARAJAS
Permit Finaled 3/13/2026 DEROLD HAUFF
CofO Issued 3/13/2026 DEROLD HAUFF
Permit Finaled 3/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/19/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/21/2023 CELINA MORENO
Sewer availability Cleared 8/21/2023 CELINA MORENO
Low Impact Development (LID) Cleared 10/17/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/18/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2024 Corrections Issued CRAIG DAVIS
Pre-Inspection 5/8/2024 Approved MICHAEL LEWIS
Underground Mechanical 5/8/2024 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 5/16/2024 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 5/21/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 6/12/2024 Partial Approval CRAIG DAVIS
Green Building Rough 6/12/2024 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 6/12/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 8/12/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/12/2024 Corrections Issued CRAIG DAVIS
Pre-Inspection 8/12/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 8/15/2024 Approved CRAIG DAVIS
PLUMBING-Rough 8/15/2024 Corrections Issued CRAIG DAVIS
Pre-Inspection 8/15/2024 Corrections Issued CRAIG DAVIS
Deputy Wood Construction 8/21/2024 Conditional Approval CRAIG DAVIS
BUILDING-Rough-Frame 9/10/2024 Partial Approval CRAIG DAVIS
Green Building Rough 9/10/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 9/10/2024 Not Ready for Inspection CRAIG DAVIS
MERV13>=Rough 9/10/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 9/10/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 9/18/2024 Approved SABAS ALONSO
Green Building Rough 9/18/2024 Approved SABAS ALONSO
HVAC-Rough 9/18/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/18/2024 Partial Approval SABAS ALONSO
MERV13>=Rough 9/18/2024 Not Ready for Inspection SABAS ALONSO
Insulation 9/24/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/24/2024 Approved ANTHONY RAMOS
Pre-Inspection 10/4/2024 Partial Approval CRAIG DAVIS
Drywall Nailing 11/7/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 5/13/2025 Not Ready for Inspection BARRY HACHE
Final 5/13/2025 Corrections Issued BARRY HACHE
HVAC-Final 5/13/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 2/17/2026 Not Ready for Inspection BARRY HACHE
Final 2/17/2026 Not Ready for Inspection BARRY HACHE
Green Building Final 2/17/2026 Corrections Issued BARRY HACHE
HVAC-Final 2/17/2026 Corrections Issued BARRY HACHE
MERV13>=Final 2/17/2026 Approved BARRY HACHE
PLUMBING-Final 2/17/2026 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready BARRY HACHE
Smoke Detectors 2/17/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 2/20/2026 Approved SABAS ALONSO
Green Building Final 2/20/2026 Approved SABAS ALONSO
HVAC-Final 2/20/2026 Corrections Issued SABAS ALONSO
PLUMBING-Final 2/20/2026 Corrections Issued SABAS ALONSO
Final 3/2/2026 Corrections Issued BARRY HACHE
HVAC-Final 3/2/2026 Approved BARRY HACHE
PLUMBING-Final 3/2/2026 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Not Ready BARRY HACHE
Smoke Detectors 3/2/2026 Approved BARRY HACHE
Final 3/6/2026 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Not Ready BARRY HACHE
Final 3/11/2026 OK to Issue CofO RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV Approved RAUL BARAJAS