15120 W LANARK ST 91402
Certificate Information: 15120 W LANARK ST 91402
- Application / Permit
- 23014-20000-02118
- Plan Check / Job No.
- B23VN06996
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Detached Garage with Addition to a Detached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 12/27/2023
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2023 | EDWIN ESPIN |
| Corrections Issued | 6/9/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/24/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/9/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 10/2/2023 | CARLOS MONTES |
| Plan Check Approved | 10/24/2023 | EDWIN ESPIN |
| Issued | 12/27/2023 | APPLICANT |
| CofO in Progress | 6/2/2025 | VINCENT HANLEY |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
| CofO Issued | 6/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 7/13/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/17/2023 | RYAN KIM |
| Construction near power lines | Cleared | 10/20/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/20/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/3/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 11/27/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 12/18/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/18/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 12/18/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/18/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/2/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/2/2025 | Approved | VINCENT HANLEY |
| Insulation | 1/27/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/27/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 2/19/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 2/19/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/4/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/22/2025 | Approved | VINCENT HANLEY |
| Final | 5/22/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 5/22/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/22/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/22/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/22/2025 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/2/2025 | Approved | VINCENT HANLEY |
| Final | 6/2/2025 | OK to Issue CofO | VINCENT HANLEY |