7270-7272 N HATILLO AVE 91306

Certificate Information: 7270-7272 N HATILLO AVE 91306

Application / Permit
23014-20000-02116
Plan Check / Job No.
B23VN06992
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21'2"X 28'2" ATTACHED GARAGE (411 SF), (N) 8'-3"X 4'-0" ADDITION (35 SF), AND 19'9" X 16'1" PORTION (325 SF) OF (E) SINGLE FAMILY DWELLING TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). WORK PER ENGINEERING.
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
CofO Issued on 6/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2023 APPLICANT
Assigned to Plan Check Engineer 6/6/2023 ISIS ARGUETA
Corrections Issued 6/7/2023 ISIS ARGUETA
Applicant returned to address corrections 6/15/2023 ISIS ARGUETA
Plan Check Approved 6/18/2023 MADISON ODELL
Issued 6/23/2023 APPLICANT
CofO in Progress 5/31/2024 ALEXANDER HANDY
Permit Finaled 6/18/2024 JOHN JANSON
CofO Issued 6/18/2024 JOHN JANSON
Permit Finaled 6/18/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/10/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/10/2023 NIKKI ZULUETA
Sewer availability Cleared 6/10/2023 NIKKI ZULUETA
Construction near power lines Cleared 6/12/2023 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/13/2023 NIKKI ZULUETA

Contact Information

Architect Karabachian,, Sevak A; Lic. No.: NA38632       ,
Contractor Hamsco Construction Co; Lic. No.: 1065709-B       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502
Engineer Arakelyan,, Aram; Lic. No.: NA82796       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2023 Conditional Approval HENRY KIM
Footing/Foundation/Slab 8/22/2023 Conditional Approval ALEXANDER HANDY
PLUMBING-Rough 8/22/2023 Partial Approval ALEXANDER HANDY
Sewer 8/22/2023 Approved ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 11/13/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 11/28/2023 Approved ALEXANDER HANDY
HVAC-Rough 11/28/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 11/28/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/8/2023 Approved ALEXANDER HANDY
Insulation 12/8/2023 Conditional Approval ALEXANDER HANDY
Interior/Exterior Lathing 12/8/2023 Partial Approval ALEXANDER HANDY
Drywall Nailing 12/21/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 12/21/2023 Approved MORRIS JACKSON
Gas Test 3/11/2024 Approved HENRY KIM
ELECTRICAL-Final 4/11/2024 Corrections Issued ALEXANDER HANDY
HVAC-Final 4/11/2024 Approved ALEXANDER HANDY
PLUMBING-Final 4/11/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Final 5/22/2024 Approved ALEXANDER HANDY
Final 5/22/2024 Corrections Issued ALEXANDER HANDY
PLUMBING-Final 5/22/2024 Approved ALEXANDER HANDY
Final 5/30/2024 OK to Issue CofO ALEXANDER HANDY
Footing/Foundation/Slab 5/30/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Approved ALEXANDER HANDY
Service/Power Release 5/30/2024 Approved ALEXANDER HANDY
Smoke Detectors 5/30/2024 Approved ALEXANDER HANDY