5314 N WILKINSON AVE 91607
Certificate Information: 5314 N WILKINSON AVE 91607
- Application / Permit
- 23014-20000-02094
- Plan Check / Job No.
- B23VN06890
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition to the front of (E) SFD.
- Permit Issued
- Issued on 7/17/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | JOSEPH RAFOLS |
| Corrections Issued | 6/5/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 6/20/2023 | FARSHAD ALIMOHAMADI |
| Issued | 7/17/2023 | APPLICANT |
| CofO in Progress | 12/5/2024 | GAREN HAYRAPETYAN |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| CofO Issued | 12/14/2024 | RUBEN SALAS |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/8/2023 | BRENNEN OBETO |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | LEE GUILBEAUX |
| Specific Plan | Cleared | 6/9/2023 | JOANNA MARROQUIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/14/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 1/29/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/13/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 3/13/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 3/13/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 3/22/2024 | Corrections Issued | JOSE AVILA |
| Shower Pan | 3/26/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/14/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 5/14/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 5/22/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/16/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/26/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 8/5/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 8/8/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/24/2024 | Approved | VINCENT HANLEY |
| Final | 10/24/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 10/24/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 10/24/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 10/24/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 10/24/2024 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 10/24/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/26/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/26/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 11/26/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/26/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 11/26/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 12/5/2024 | OK to Issue CofO | GAREN HAYRAPETYAN |