13605 W GAULT ST 91405
Certificate Information: 13605 W GAULT ST 91405
- Application / Permit
- 23014-20000-02069
- Plan Check / Job No.
- B23VN06827
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 59'-2" X 34'-9" ) TO (E) SINGLE FAMILY DWELLING FOR (3) NEW BEDROOMS, (3) BATHROOMS AND FAMILY ROOM. WORK PER WFPP.
- Permit Issued
- Issued on 10/13/2023
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/2/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/28/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 10/11/2023 | ROSENDO MEDINA |
| Issued | 10/13/2023 | APPLICANT |
| CofO in Progress | 11/15/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
| CofO Issued | 11/22/2024 | RUBEN SALAS |
| Permit Finaled | 11/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/12/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/18/2023 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 9/21/2023 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/5/2023 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 12/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/13/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Approved | JOSE AVILA |
| Deputy Wood Construction | 1/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 1/23/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/1/2024 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 3/1/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 3/1/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/1/2024 | Partial Approval | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 3/7/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 3/21/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/21/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/27/2024 | Approved | JOSE AVILA |
| Green Building Rough | 3/27/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 4/1/2024 | Approved | JOSE AVILA |
| Shower Pan | 4/1/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/7/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 6/7/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/5/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/5/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 11/5/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 11/5/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/5/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/5/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/14/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/14/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 11/14/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 11/14/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/14/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | OGANES TARAKHCHYAN |