6614 N COSTELLO AVE 91405

Certificate Information: 6614 N COSTELLO AVE 91405

Application / Permit
23014-20000-02058
Plan Check / Job No.
B23VN06772
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW GROUND FLOOR ADDITION AND STR. REMODEL TO (E) 1-STORY SFD.
Permit Issued
Issued on 7/27/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 MAHNAZ NOURHASHEMI
Corrections Issued 6/16/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 6/23/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/19/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 7/25/2023 MAHNAZ NOURHASHEMI
Issued 7/27/2023 APPLICANT
CofO in Progress 3/11/2024 RYAN SALAZAR
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/26/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/26/2023 CARLOS AGUILERA
ZA Case Cleared 6/27/2023 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2023 Corrections Issued RYAN SALAZAR
Pre-Inspection 8/11/2023 Partial Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 9/6/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/24/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 10/24/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/24/2023 Approved RYAN SALAZAR
Insulation 11/1/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 11/1/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 2/27/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 2/27/2024 Approved RYAN SALAZAR
Final 2/27/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 2/27/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/27/2024 Approved RYAN SALAZAR
Final 3/6/2024 OK to Issue CofO RYAN SALAZAR