5125 N ALHAMA DR 91364

Certificate Information: 5125 N ALHAMA DR 91364

Application / Permit
23014-20000-02054
Plan Check / Job No.
B23VN06770
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW GROUND FLOOR ADDITION TO (E) 1-STORY SFD WITH INT. & EXT. STR. REMODOL
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO in Progress on 4/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 MAHNAZ NOURHASHEMI
Corrections Issued 6/20/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 6/27/2023 GARO TELMI
Plan Check Approved 7/31/2023 MAHNAZ NOURHASHEMI
Issued 8/30/2023 APPLICANT
CofO in Progress 4/24/2026 JOHN HAYES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/12/2023 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 7/13/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/13/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/13/2023 LEE GUILBEAUX

Contact Information

Contractor Construction Masters; Lic. No.: 762655-B       ,
Contractor Moshe Cohen Incorporated; Lic. No.: 762655-B       ,
Engineer Kang,, Danniel; Lic. No.: S6242 1176 N KNOLLWOOD CT      ANAHEIM, CA 92801

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2023 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 9/13/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 9/28/2023 Partial Approval PETER FOLLING
Green Building Rough 9/28/2023 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 10/6/2023 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval SEAN HAUPT
Deputy Wood Construction 10/12/2023 Approved PETER FOLLING
ELECTRICAL-Rough 10/12/2023 Corrections Issued PETER FOLLING
HVAC-Rough 10/12/2023 Approved PETER FOLLING
PLUMBING-Rough 10/12/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 11/13/2023 Approved MORRIS JACKSON
Green Building Rough 11/13/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/13/2023 Approved MORRIS JACKSON
Insulation 11/17/2023 Approved SEAN HAUPT
Drywall Nailing 11/21/2023 Approved JOHN KIDWELL
Final 12/15/2023 Corrections Issued MORRIS JACKSON
Green Building Final 12/15/2023 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Approved MORRIS JACKSON
Smoke Detectors 12/15/2023 Approved MORRIS JACKSON
Final 1/30/2026 Corrections Issued JOHN HAYES
Final 4/24/2026 OK to Issue CofO JOHN HAYES