13347 W GARBER ST 91331

Certificate Information: 13347 W GARBER ST 91331

Application / Permit
23014-20000-02046
Plan Check / Job No.
B23VN06755
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING RECREATION ROOM TO ADU WITH ADDITION PER ORDINANCE.
Permit Issued
Issued on 6/5/2023
Issuing Office
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/23/2023 JOHNPAUL ISIP
Corrections Issued 5/26/2023 JOHNPAUL ISIP
Plan Check Approved 6/4/2023 FARSHAD ALIMOHAMADI
Issued 6/5/2023 APPLICANT
CofO in Progress 11/16/2023 MICHEL ABAJAN
Permit Finaled 12/6/2023 RUBEN SALAS
CofO Issued 12/6/2023 RUBEN SALAS
Permit Finaled 12/6/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/30/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 5/30/2023 NIKKI ZULUETA
Sewer availability Cleared 5/30/2023 NIKKI ZULUETA
Clean Up Green Up Cleared 5/31/2023 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 6/1/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2023 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 7/10/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 7/10/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 7/10/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 8/10/2023 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/29/2023 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 8/29/2023 No Access for Inspection MICHEL ABAJAN
Green Building Rough 8/29/2023 No Access for Inspection MICHEL ABAJAN
METHANE-Rough 8/29/2023 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 8/29/2023 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/5/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/19/2023 Approved MICHEL ABAJAN
Shower Pan 9/19/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/22/2023 Approved MICHEL ABAJAN
Wood Frame 9/22/2023 Approved MICHEL ABAJAN
Insulation 9/26/2023 Approved MICHEL ABAJAN
Drywall Nailing 9/29/2023 Approved MICHEL ABAJAN
Green Building Rough 9/29/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/8/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/8/2023 Approved MICHEL ABAJAN
Final 11/8/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 11/8/2023 Approved MICHEL ABAJAN
HVAC-Final 11/8/2023 Approved MICHEL ABAJAN
METHANE-Final 11/8/2023 Approved MICHEL ABAJAN
METHANE-Rough 11/8/2023 Approved MICHEL ABAJAN
PLUMBING-Final 11/8/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/8/2023 Approved MICHEL ABAJAN
Smoke Detectors 11/8/2023 Approved MICHEL ABAJAN
Final 11/16/2023 OK to Issue CofO MICHEL ABAJAN